
Summary: This medium-scale solar project in Victoria is designed to generate clean energy, significantly contributing to the region’s renewable energy goals. The project features advanced photovoltaic technology with a total DC capacity of 6.12 MW. It includes solar photovoltaic (PV) modules connected to the distribution network at 11 kV and is currently under construction.
Project Highlights:
- Capacity: 6.12 MW DC of clean energy generation
- Technology: Bifacial monocrystalline PV modules
- Inverters: 1 Sungrow inverter
- PV Modules: Approximately 11,232 PV modules
- Tracking System: Single-axis tracking
- Grid Connection: Connected to the distribution network at 11 kV, managed by AusNet Services
- Current Status: Under construction
ElectraGlobe’s Scope: ElectraGlobe was responsible for the detailed electrical design and construction support, ensuring compliance with Australian and international standards. Our work included:
Detailed Electrical Design Inclusions:
- Concept to Issue for Construction (IFC) Package:
- Development of a comprehensive design package from the initial concept phase to detailed IFC documents.
- PV Array Configuration:
- Design of PV module strings and sub-arrays interconnected through DC string cables and combiner boxes.
- Incorporation of DC combiner boxes and inverter DC bus systems.
- Layout and blocking plans based on optimal tracker orientation and module placement.
- DC Reticulation:
- Detailed design of DC electrical connections from PV modules to combiner boxes and inverters.
- Analysis and optimization of DC voltage levels and compliance with standards.
- Detailed cabling design including sizing, voltage drop, and current carrying capacity assessments.
- Earthing and Lightning Protection:
- Development of earthing and lightning protection systems in compliance with AS 1768 and IEEE80 standards.
- Soil resistivity analysis and earthing design to ensure safety and system reliability.
- MV Cable Design and Reticulation:
- Medium voltage cable design and reticulation in accordance with relevant codes and standards.
- Inclusion of MV cable rating studies, layout drawings, and trench profiles.
- SCADA and Communication Systems:
- Construction Support:
- Providing technical support during the construction phase to ensure adherence to design specifications and industry standards.
Capacity
6.12 MW DC of clean energy generation
Technology
Bifacial monocrystalline PV modules
Inverters
1 Sungrow inverter
PV Modules
Approximately 11,232 PV modules
Tracking System
Single-axis tracking
Grid Connection
Connected to the distribution network at 11 kV, managed by AusNet Services
Current Status
Under construction