Agrivoltaics in Australia: Engineering a Solar Farm for Sheep Grazing

Agrivoltaics in Australia most often means sheep grazing under a utility-scale solar farm, and it works with standard single-axis trackers. The plant does not need to be raised or re-engineered. It does need module clearance, cabling, fencing and water designed for stock from the start, because retrofitting those details after construction costs more and works worse.

Why Grazing: Vegetation, Approvals and the Community

Every solar farm has to manage the ground cover under its arrays. Grass that grows past the lower module edge shades the bottom cells, raises fire risk and hides damaged cabling. Slashing, mowing or spraying is a recurring O&M cost with machinery working close to piles and string cables.

Sheep do the same job continuously, at low cost, and without heavy equipment between rows. For the landowner, the land stays in agricultural production and keeps an income stream on top of the lease.

Two other reasons matter:

  • Land-use approvals. Planning authorities and state guidance increasingly ask how a solar farm affects agricultural land. A credible grazing plan, written into the development application, answers that question directly. See our guide to solar farm development approval in Australia for how the approval pathway works.
  • Community acceptance. Neighbours and councils tend to respond better to a project that keeps the land farmed.

The Design Parameters That Change

These are indicative design inputs, not code requirements. Final values depend on the tracker product, the site wind region and what the grazier and asset owner agree.

ParameterStandard (mowed) designGrazing-ready designWhat drives it
Lower module edge at maximum tiltSet by tracker product, often well under a metreConfirm it clears sheep and the expected pasture height; raise only if the stock or pasture needs itTracker hub height, module length, maximum tilt angle
Row pitchOptimised for yield, land and cable costUsually unchanged for sheep; widen only for machinery or croppingGround coverage ratio, shading losses, land available
Tracker stow and night positionProduct defaultConsider stow angles and night positions that keep the lower edge clear of stockTracker control settings, wind stow strategy
String cable managementClipped to module frames and torque tubesFully secured, no slack loops, harnesses kept above stock reachSheep chew and rub on loose cable
Above-ground equipmentInverter and combiner enclosures open to the arrayStock-proof guards or fencing around inverter stations, combiner boxes and cable risersRubbing, chewing, damage to doors and glands
Internal fencingPerimeter security fence onlyPerimeter plus internal paddocks for rotational grazingPasture management, stock handling

Module clearance

The critical number is the lower edge of the module at its steepest tilt. Sheep need to move under and between rows without rubbing the glass or frames, and pasture under the modules should stay below the lower edge between grazing rotations.

For sheep, most standard tracker products work as supplied. If the clearance is marginal, there are cheaper options than raising the whole structure, such as limiting the maximum tilt angle in the tracker controller, at a small cost in yield.

Row pitch

Sheep do not need extra space between rows, so pitch is set by the usual yield, land and cable trade-off. Wider pitch matters only if machinery or crops work between rows. Our article on solar farm design essentials covers how pitch and layout are optimised.

Tracker stow positions

Wind stow and night-time positions are set in the tracker control system. On a grazing site, check that none of the stow positions puts a module edge where stock will hit it.

Cable and Equipment Protection

Cabling is where grazing causes the most damage. Sheep chew loose cable and rub on anything at shoulder height.

Underground cabling

Buried cabling is designed to AS/NZS 3000 and the project specification regardless of grazing, with the depth and mechanical protection that standard requires. Grazing changes the transition points, not the trench. Every place a cable comes out of the ground, at a combiner box, an inverter station or a tracker row, needs a riser in conduit or a guard so it cannot be chewed or pushed out of position.

Compact and reinstate trench backfill properly. Stock will open up soft trench lines after rain.

String cabling under the modules

On most sites the exposed DC string cables are the main concern. Good practice is:

  • Clip every string cable to the module frame or torque tube with UV-rated fixings at close spacing. No slack loops.
  • Run string harnesses and jumpers between rows in a cable tray or on a messenger wire, above the reach of stock.
  • Include a cable inspection walk in the O&M plan, timed with grazing rotations.

Above-ground equipment

Inverter stations, PCS skids, combiner boxes and the substation should all be stock-proof. That means a fenced compound around the substation and BESS, and guards or small enclosures around inverter stations and combiner boxes. On projects we have commissioned, the cost of guarding equipment during construction is small next to repairing damaged glands, doors and cables after stock are on site.

Fencing, Gates, Water and Stock Handling

A solar farm perimeter fence is a security fence first. It usually holds sheep without modification, but grazing adds internal requirements:

  • Internal paddocks. Rotational grazing needs the array split into paddocks with stock fencing. Align fence lines with internal access tracks and block boundaries so they do not cross cable routes or tracker rows awkwardly.
  • Gates. Gates need to suit both maintenance vehicles and stock movement. Place them at track intersections, and make sure that a closed gate never blocks emergency access.
  • Water. Troughs and pipelines need to sit at paddock edges, away from inverter stations and clear of cable trenches. Coordinate water pipe routes with the cable layout early, so the two do not compete for the same corridor.
  • Stock handling. Yards and loading ramps are best placed outside the array, with truck access that does not run through the plant.

The grazier is also working inside an operating high-voltage site. The grazing agreement should cover site induction, access rules, permits near energised equipment, notification of damage, working dogs, biosecurity and insurance. Land and access questions are covered in our land assessment guide.

Yield and Cost Trade-Offs

Grazing on its own does not reduce energy output. A plant designed for sheep with standard trackers and standard row pitch has the same yield model as a mowed plant. If anything, consistent vegetation control avoids the shading losses that come from long grass on the lower module edge.

The trade-offs come from design changes made to suit grazing:

Design changeCost effectYield effect
Higher tracker hub heightLonger piles, higher wind loads on the structure, more steelNeutral, unless pitch also changes
Limiting maximum tilt to improve clearanceNo capital costSmall loss in early morning and late afternoon output
Wider row pitchMore land, longer cable runs, more fencingLower shading losses per row, fewer MW per hectare
Cable trays, guards and stock-proof enclosuresModest capital costNeutral; reduces outage risk from cable damage
Internal fencing and waterModest capital cost, usually shared with the grazierNeutral
Grazing instead of mowingLower vegetation management cost over the asset lifeNeutral to slightly positive

The operating risks, such as cable damage, dust near modules and a third party on site, are mostly design and contract issues. That is why grazing should be decided at concept stage.

Reported effects of array shade on pasture, wool or meat vary between sites and studies. Treat any agricultural benefit as upside, and make the plant stand on its energy yield alone.

Other Agrivoltaic Uses

Other uses ask more of the design:

  • Cropping between rows needs row pitch wide enough for farm machinery, plus headlands for turning. That lowers MW per hectare and changes the land and cable economics.
  • Horticulture under the array generally needs elevated structures with much higher clearance, which raises structural and civil cost considerably.
  • Cattle are rarely compatible with standard solar plant. They are heavier, taller and much more likely to damage structures and cabling.
  • Apiary and native vegetation are low-impact options that need little design change beyond access.

For site-level questions about which land suits which use, see our article on solar farm site selection in Australia.

Design a Grazing-Ready Layout

Grazing decisions are cheapest at concept design, when tracker selection, clearance, layout, fencing and cable routes are still open. ElectraGlobe's concept design services include layout options that test these trade-offs before the design is locked in. Our article on what the concept design phase delivers explains the wider scope. Get in touch to talk through a grazing-ready layout for your site.

Frequently Asked Questions

Can sheep graze under solar panels?

Yes. Sheep grazing is the most common form of agrivoltaics in Australia, and it works with standard single-axis tracker plant. The design needs secured cabling, stock-proof guards around equipment, internal fencing and water, all planned before construction.

How high do panels need to be for grazing?

For sheep, the lower module edge at maximum tilt needs to clear the animals and the pasture height between rotations. Where clearance is marginal, limiting the maximum tilt angle is often cheaper than raising the structure. Confirm the figure with the tracker supplier for the specific product and site.

Does grazing reduce solar farm output?

Grazing itself does not reduce output. A grazing site with standard trackers and row pitch has the same yield model as a mowed site, and good vegetation control avoids shading from long grass. Output only changes if the design is altered for grazing, for example by limiting tilt or widening row pitch.

Do cattle work with solar farms?