Grid Connection Studies

Getting a renewable energy project connected to the Australian grid is one of the most technically demanding and commercially critical phases of project development. ElectraGlobe manages the full grid connection process, handling the technical complexity on your behalf and keeping your connection timeline on track.

Our grid connection services cover the full application process with all distribution and transmission network service providers across Australia, from preliminary feasibility through to Dynamic Model Acceptance Testing.

What Are Grid Connection Studies?

Grid connection studies are the technical analyses required to assess how a new generator or storage system will interact with the existing electricity network at the proposed connection point.

The Core Studies

  • Power flow analysis: steady-state voltages, thermal loading and power transfer at the connection point
  • Fault level assessment: short circuit contribution and equipment fault rating adequacy
  • Protection coordination: grading, settings and network protection unit configuration
  • Dynamic stability: system response to faults, disturbances and network events
  • Voltage regulation: voltage rise, step change and reactive power capability

These studies form the technical basis of your connection enquiry and must satisfy the requirements of the relevant network service provider before an offer to connect is issued.

What ElectraGlobe Delivers

Our scope is set by the stage your project is at and by how much of the connection work your internal team already covers.

Connection Process ManagementWhat we deliver
FeasibilityPreliminary feasibility assessment and connection point pre-screening
EnquiryDetailed connection enquiry preparation and submission
NSP reviewTechnical response management while the NSP assesses the application
Offer to connectOffer review and negotiation support
AgreementGrid connection agreement execution support
Model acceptanceDynamic Model Acceptance Testing (DMAT)
Technical StudiesWhat we deliver
Load flowLoad flow and power transfer analysis
Fault levelFault level and short circuit analysis
ProtectionProtection coordination and network protection unit settings
AutomationPython scripting and automation for large data sets and multiple NSP scenarios
CommissioningWitness testing and injection testing for protection relay commissioning
Standards and ComplianceWhat we deliver
AS 4777.2Compliant protection settings for inverter-based generators
DNSP requirementsTechnical requirements met for all Australian states
TNSP requirementsConnection requirements for large-scale generators

Network Service Providers We Work With

We have established working relationships with all major NSPs across Australia.

StateNetwork service providers
NSWAusgrid, Essential Energy, Endeavour Energy
VICPowercor, CitiPower, United Energy, AusNet Services, Jemena
QLDErgon Energy, Energex
SASA Power Networks
TASTasNetworks
WAHorizon Power, Western Power
ACTEvoenergy

Each provider sets its own technical requirements, submission formats and review timelines, and knowing them before the enquiry is lodged is what keeps a connection on programme.

Frequently Asked Questions

What is a grid connection study?

A grid connection study shows how a proposed generator or battery will behave on the network at its connection point: how it affects voltages and thermal loading, how much fault current it adds, how its protection coordinates with the network and how it rides through faults and disturbances. The network service provider relies on these studies before it will make an offer to connect.

How long does a grid connection take in Australia?

It depends heavily on the network, the connection point and the size of the project. Transmission connections that need AEMO's involvement and full dynamic studies take considerably longer than small distribution connections. Starting the studies early and lodging a complete, well-supported application is the most reliable way to shorten the timeline.

Do you handle both DNSP and TNSP connections?

Yes. We prepare and manage applications with distribution and transmission network service providers in every state, including the AEMO GPS process for projects that need it.

What documents does a connection application need?

That varies by provider and project size, but typically includes single-line diagrams, equipment data, protection settings, power system models and the study reports themselves. Our guide below lists what a DNSP usually asks for.