A BESS factory acceptance test (FAT) proves, before anything ships, that the equipment was built to the approved design and works as specified. The manufacturer runs it, and the owner, the EPC contractor and usually an owner's engineer witness it. The four equipment groups worth witnessing are the switchboards and MV gear, the power conversion system (PCS) and transformers, the battery management system (BMS), and the energy management system (EMS) and plant controls.
A defect found in the factory costs a day and a re-test. Found on site after shipping and termination, it costs weeks and often lands on the critical path for energisation.
FAT vs SAT vs Commissioning
The three stages are often blurred in contracts and in conversation. They test different things, and none of them replaces another.
| Stage | Where | What it proves | Who usually attends |
|---|---|---|---|
| Factory acceptance test (FAT) | Manufacturer's factory | Equipment is built to the approved drawings and functions correctly as a unit | Manufacturer, EPC, owner or owner's engineer |
| Site acceptance test (SAT) | Project site, after installation | Equipment survived transport and was installed and terminated correctly | EPC, installer, owner's engineer |
| Commissioning | Project site, energised | The integrated plant works with the network, meets its performance standards and is safe to operate | EPC, OEMs, owner's engineer, network service provider and AEMO where required |
The FAT is the last point where the owner can inspect the equipment with the doors open and the factory engineers in the room.
Switchboards and MV Gear
Switchboards are where a BESS FAT most often turns up real problems, because they are custom-built from project drawings that keep changing. A typical lineup covers LV and MV incomers, feeders, auxiliary boards and protection relay panels.
Visual and Construction Checks
Start with the physical build against the approved general arrangement and schematic drawings.
- Drawing revision. Confirm the factory built to the current approved revision, not an earlier one. This is the single most common source of findings.
- Nameplates and labelling. Ratings, circuit designations and cable labels should match the single-line diagram.
- Busbar and wiring. Check torque marks on bolted connections, segregation of control wiring from power, ferrule numbering and that spare terminals were provided as specified.
- Form of separation and IP rating. Compare against the specification, typically referenced to AS/NZS 61439 for LV assemblies.
- Termination space. Check that cable entry, gland plates and terminals suit the cable sizes on the cable schedule.
Insulation and Dielectric Testing
Witness insulation resistance (IR) testing of the main circuits and the dielectric (power frequency withstand) test. Record the test voltage, duration, ambient conditions and the instrument's calibration certificate number. An IR result with no recorded test voltage is not a useful record.
Functional and Protection Checks
Functional tests prove the board does what the schematics say.
- Operate every circuit breaker and switch, locally and remotely where specified.
- Check mechanical and electrical interlocks, including earth switch interlocks on MV gear.
- Prove trip circuits from each protection relay output through to the breaker.
- Confirm the relay settings loaded match the issued protection settings file, and that the relay firmware version is recorded.
- Run secondary injection on the protection relays to confirm pickup and trip.
CT and VT Checks
Current and voltage transformers are easy to get wrong and hard to fix once cables are terminated. Witness ratio and polarity checks, confirm the CT class and burden match the protection and metering design, and check that the CT secondary is earthed at one point only. For revenue metering CTs and VTs, confirm the certificates the metering provider needs are in the FAT record.
PCS and Transformers
The PCS and step-up transformer are usually standard products, so the FAT is more about confirming project configuration and routine test results than build quality.
Transformer Routine Tests
For power transformers, witness or review the manufacturer's routine tests, typically to the AS/NZS 60076 series:
- Winding resistance
- Voltage ratio and vector group
- Short-circuit impedance and load loss
- No-load loss and current
- Insulation and applied or induced voltage tests
Compare the measured impedance and losses against the guaranteed values in the contract. Impedance in particular feeds the grid connection studies and the power system models, so a value outside tolerance can ripple into the connection process.
PCS Control Functions
For the inverter skid, focus on project-specific configuration:
- Firmware version, recorded and matched against the version used in the power system models
- Active and reactive power setpoint response
- Grid protection settings loaded as issued
- Auxiliary supply, cooling and HVAC operation
- Fault and alarm signalling to the plant controller
Firmware matters more than it looks. The PSS/E and PSCAD models submitted for connection approval represent a specific firmware and parameter set, and a different shipped version has to be explained to the network service provider and AEMO later.
BMS, EMS and Controls
Cells are tested by the manufacturer at module and rack level, which owners rarely witness. What the owner should witness is the control and protection layer that decides how the battery behaves.
Alarms and Protection
Walk through the BMS alarm and trip list. Simulate a representative sample of conditions, such as over-temperature, cell over-voltage and under-voltage, communication loss and fire panel inputs, and confirm the system responds as the functional description says: alarm, derate, or open the DC contactors.
Interlocks
Prove the safety interlocks between the BMS, PCS, fire systems and switchgear, and record each test against the interlock matrix.
Communications and Points Lists
Check the communications from BMS to EMS to plant controller to SCADA against the points list. Every point should map correctly, with the right scaling, units and sign convention. Sign convention errors on charge and discharge power are common and cause confusion at commissioning.
Where the full plant controller cannot be tested in the factory, agree in advance which functions are proven at FAT and which are deferred to site, and record that split in the inspection and test plan.
Paperwork to Demand
A FAT is only as good as its records. A test witnessed but not documented and signed is hard to rely on in a dispute or warranty claim.
Records to Have Before Leaving the Factory
- Approved ITP: the inspection and test plan issued before the FAT, with hold and witness points marked
- Drawing set: the approved revision the equipment was built to, marked up with any deviations
- Calibration certificates: in-date certificates for every test instrument used
- Completed test sheets: actual measured values, not just pass marks, signed by the manufacturer and witnesses
- Settings and firmware record: protection settings, control parameters and firmware versions as loaded
- Punch list: every open item with an owner, a close-out method and whether it blocks shipment
- Release to ship: a signed statement of which items may ship and on what conditions
The punch list deserves care. Classify each item as either closed before shipment, closed at site by the manufacturer, or closed at site by the installer. Items left loosely defined at FAT become site variations.
Lessons From ElectraGlobe FATs
On the switchboard and BESS FATs we have witnessed, the findings tend to fall into a handful of familiar categories rather than dramatic failures.
Drawing Revisions Drift
The most frequent issue is a build that matches a superseded drawing, because late changes to a protection scheme or auxiliary circuit do not always reach the factory floor. Check panel drawing revisions against the issued register first.
Termination Space and Cable Entry
Gland plates and terminals sized for a smaller cable than the schedule now requires are a recurring find. In the factory it is a modification; on site it can mean cutting steel or re-routing cables.
Settings Not Yet Final
Relays and controllers often arrive with preliminary settings because the studies behind the final settings are still running. That is fine if the record says so and a site test is planned, and a problem if everyone assumes the FAT proved them.
Incomplete Records
Test sheets with ticks but no measured values, or instruments without current calibration certificates, are common. Ask for the corrected records before signing the release.
The same principle sits behind a golden table review on a solar farm: inspect the first unit hard, while fixing it is still cheap.
Book an Owner's Engineer for Your FAT
FAT witnessing is a core part of owner's engineering on BESS projects. For context on where FAT sits in the wider program, see our guide to BESS project development in Australia.
ElectraGlobe's owner's engineering services cover ITP review, FAT and SAT witnessing, and commissioning oversight for solar and BESS projects across Australia and New Zealand. If you have a FAT coming up, contact our team to talk through the scope.
Frequently Asked Questions
What is tested at a BESS factory acceptance test?
A BESS FAT typically covers the switchboards and MV gear, the PCS and transformers, and the BMS, EMS and control systems. Tests include visual and construction checks, insulation and dielectric tests, protection and interlock checks, CT and VT ratio and polarity, transformer routine tests, and alarm and communications checks against the points list. The exact scope should be set out in the inspection and test plan agreed before the FAT.
Should the owner attend the FAT in person?
For custom-built equipment such as switchboards and protection panels, in-person witnessing by the owner or an owner's engineer is strongly recommended, because much of the value comes from physically inspecting the build. For standard products with well-documented routine tests, a review of test records or a remote witness can be acceptable. The decision should reflect the equipment's risk and how hard it would be to fix on site.
What happens if equipment fails a FAT?
The failure is recorded on the punch list, the manufacturer corrects it, and the affected test is repeated and witnessed again. Minor items may be released to ship with an agreed site close-out, but anything affecting safety, protection or contractual performance should normally be closed before shipment. The contract and ITP should define who pays for re-testing and any extra witness travel.
How long does a switchboard FAT take?
A small lineup can be witnessed in a day, while a large MV and LV lineup with protection panels often takes two to four days. The main drivers are the number of panels, the amount of protection secondary injection and functional testing, and how ready the factory is on the day. Equipment presented with incomplete wiring or missing records can easily double the time.