There is no single Australian standard for utility-scale BESS fire safety. Instead, approvals rely on a combination of standards: AS/NZS 5139, which has a limited scope; NFPA 855, which is US-based; UL 9540A test data for the specific product; and a site-specific fire risk assessment. Together they show how a battery fire would behave and how the layout keeps it contained.
This guide maps those standards and the documents approvals commonly expect.
The Standards Map
The table shows the documents most often cited. Whether each applies, and how strictly, depends on system size, jurisdiction and the approval authority. Confirm scope and edition against the current published text.
| Standard | What it covers | Relevance to utility-scale BESS | Who typically asks for it |
|---|---|---|---|
| AS/NZS 5139 | Electrical installation safety of battery systems used with power conversion equipment | Written mainly for building-mounted and smaller installations. How far it applies to containerised grid-scale systems should be agreed with the authority | Electrical regulators, DNSPs, designers as a baseline |
| AS/NZS 3000 | Wiring Rules, general electrical installation safety | Applies to the LV installation around the battery | Electrical regulators |
| NFPA 855 | Installation of stationary energy storage systems, including spacing, detection, suppression and explosion control | US standard, widely used in Australia as a reference for good practice. Check which edition is being cited | Fire authorities, planning consultants, insurers |
| UL 9540 | Safety certification of an energy storage system as a whole | Product-level evidence that the system has been evaluated | Owners, insurers, approval authorities |
| UL 9540A | Test method for thermal runaway fire propagation at cell, module, unit and installation level | Main evidence for how a fire behaves and spreads in the chosen product | Fire engineers, fire authorities, insurers |
| IEC 62933-5-2 | Safety requirements for grid-integrated electrochemical energy storage systems | International reference, increasingly cited in supplier documentation | Owners' engineers, lenders' advisors |
| State fire authority guidance | Expectations for renewable energy facilities, including access, water supply and emergency planning | Varies by state and changes over time. Check the current version for the site | Fire services during planning referral |
NFPA 855 and UL 9540A are not Australian law. They matter because approval authorities, fire services and insurers adopt them as the reference for acceptable practice. AS/NZS 5139 alone rarely settles the question for a grid-scale project, and an application that relies only on it tends to attract requests for further information.
UL 9540A Test Evidence: What Each Level Shows
UL 9540A is a test method, not a pass or fail certification. It shows what happens when a cell goes into thermal runaway and whether the event spreads. Testing moves to the next of four levels only if the previous one shows the hazard was not contained.
Cell level
A single cell is forced into thermal runaway, typically by heating it. The test records the temperature at which venting and thermal runaway start, and the volume and composition of the gas released. This gas data is important. Battery off-gas is flammable, and its volume drives the deflagration and explosion control design for enclosed units.
Module level
The test checks whether thermal runaway in one cell spreads to neighbouring cells within the module. It also measures heat release and gas generation at that scale. If propagation does not continue beyond the initiating cell, the module result may be enough for some purposes.
Unit level
The full battery rack or enclosure is tested with one module in thermal runaway. This level shows whether fire spreads to adjacent racks, how hot the enclosure surfaces become, and whether flaming or projectiles escape the enclosure. For outdoor containerised products, the unit-level report is often the most useful document in the application.
Installation level
This level tests the unit with its intended fire protection, such as a specific suppression system. It is generally needed only when unit-level results do not demonstrate containment.
When reviewing supplier data, check which cell chemistry and product revision was tested, and whether that configuration matches what is being bought. A report for an earlier product generation can mislead a fire risk assessment.
Separation, Spacing and Firefighting Access
The most common question we hear is how far apart battery containers need to be. There is no universal Australian figure, and this guide does not give one. Separation distances on a real project come from a combination of three things:
- Product test data. UL 9540A unit-level results show whether fire spreads to an adjacent unit at the tested spacing and what heat flux reaches neighbouring surfaces.
- Manufacturer installation requirements. Suppliers specify minimum clearances that their test evidence supports. Building closer than this can void warranties and undermine the safety case.
- Site-specific assessment. A fire engineer models radiant heat to adjacent units, to site boundaries, to the substation and control buildings, and to surrounding vegetation, then confirms the layout against it.
How layouts respond
Layout decisions follow from that assessment. Typical responses include:
- Grouping units into blocks with wider fire breaks between them, so a single event is limited to one block
- Keeping sufficient clearance from the substation, control room, O&M buildings and site boundary
- Providing a cleared, maintained asset protection zone around the battery area, which matters a great deal on rural sites with bushfire exposure
- Placing access roads so fire vehicles can approach from more than one direction and turn around without reversing
- Sizing and locating water supply, whether tanks, hydrants or both, according to what the fire authority expects for cooling of exposed units
Spacing is also a commercial decision. Wider spacing uses more land, cable and earthing grid. Tighter spacing brings heavier suppression, stricter conditions and harder insurer conversations. Settle the trade-off at concept stage. Our guide to BESS project development in Australia covers those earlier phases.
Fire Risk Assessment, Emergency Response Plan and Fire Authority Consultation
Fire safety now forms a standard part of most BESS planning applications. Requirements differ by state and by assessment pathway, but the document set usually looks similar.
Documents planning approvals commonly ask for
- Fire risk assessment or fire safety study for the battery and its surroundings
- Hazard identification covering thermal runaway, off-gas, explosion and smoke
- Separation and radiant heat assessment supporting the layout
- UL 9540A test reports and product certification for the selected system
- Emergency response plan for site staff and attending fire crews
- Bushfire risk assessment and asset protection zone design
- Water supply and firefighting access plan
- Smoke and contaminated firewater management approach
Fire risk assessment
The fire risk assessment is the central document. It identifies credible fire scenarios, assesses consequences on and off site, and shows how the design controls them. Generic text written before the supplier is chosen tends to attract conditions requiring a revised assessment once the product is selected.
Emergency response plan
The emergency response plan tells site staff and fire crews what to do: isolation, safe approach distances, whether to apply water or let a unit burn out while cooling neighbours, and how long to monitor afterwards. Fire services generally want it to match the specific product.
Fire authority consultation
In most states the planning authority refers BESS applications to the relevant fire service, or expects evidence that the applicant has consulted it. Some state fire authorities have published guidance for renewable energy facilities that sets out their expectations for access, water and emergency planning. Check the current version for the state you are building in, since these documents are revised. Engaging the fire service early, before the layout is fixed, avoids redesign after submission. Our guide to solar farm development approval in Australia covers the wider planning process, and much of it applies to standalone and co-located storage.
Design Levers: Where Engineering Changes the Risk
Enclosure choice
Outdoor modular cabinets that are not entered by people, and walk-in containers, are very different. Non-walk-in units reduce exposure for personnel and usually simplify the explosion control design. Walk-in containers need explosion venting or gas detection with active ventilation, plus clear rules for entry after an alarm.
Detection and suppression
Off-gas detection can flag a failing cell before smoke or heat detection would. Suppression varies by product: clean agent or aerosol, water, or a design that contains an event without active suppression. The right choice depends on the product's test evidence and on what the fire authority will accept. Adding more suppression is not always safer. A gaseous agent can, for example, suppress flame while flammable gas continues to accumulate.
BMS protection
The battery management system is the first line of defence. Cell-level voltage and temperature monitoring, protection against overcharge and over-discharge, and correct shutdown sequencing prevent most of the conditions that start thermal runaway. Interfaces between the BMS, the power conversion system, the fire panel and SCADA need to be designed and tested as one system. Our explainer on what a battery energy storage system is covers how these components fit together.
Layout and electrical design
Electrical design matters too: isolation points crews can reach safely, protection that clears faults quickly, earthing that limits touch voltages, and cable routes that do not create a fire path between blocks. On co-located sites, the BESS layout also has to work with the PV array and the substation. Our guide to hybrid solar and BESS in Australia covers those interfaces.
Safety Note
This article is a general guide to the standards and approval documents that commonly apply to battery storage in Australia. It is not fire safety advice for any particular site. Separation distances, suppression strategy and emergency procedures for a real project must come from a qualified fire safety engineer working with the product's test data, the manufacturer's requirements and the relevant fire authority.
Engineer a Compliant BESS Layout
The fire safety case is strongest when the electrical, civil and fire design are developed together, not added to the layout afterwards. ElectraGlobe's detailed engineering team produces the layouts, single-line diagrams, earthing and protection design that a BESS fire risk assessment depends on. We work alongside your fire engineer so the drawings and the safety case match. Talk to our team about your storage project.
Frequently Asked Questions
Does AS/NZS 5139 apply to utility-scale batteries?
AS/NZS 5139 covers the electrical installation safety of battery systems used with power conversion equipment. It was written mainly with building-mounted and smaller installations in mind. For containerised grid-scale systems, it is usually treated as one reference among several rather than the governing standard. Confirm its applicability with the approval authority and your electrical designer.
What is UL 9540A testing?
UL 9540A is a test method that measures how thermal runaway starts and spreads in a battery product. Testing progresses from cell to module, unit and installation level, and records gas release, heat release and whether fire spreads. It produces data rather than a pass or fail result. Fire engineers use that data to support separation and suppression decisions.
How far apart must battery containers be?
There is no single prescribed Australian distance. Spacing on a real project comes from the product's UL 9540A results, the manufacturer's installation requirements and a site-specific radiant heat assessment by a fire engineer. Fire authority expectations for access and water supply also shape the final layout.
Do fire authorities review BESS planning applications?
In most cases, yes. Planning authorities commonly refer BESS applications to the relevant state fire service, or expect evidence that the applicant has consulted it. Some fire authorities have published guidance for renewable energy facilities, so check the current version for your state and engage early.