A BESS grid connection in Australia follows the same NER Chapter 5 path as a solar farm: enquiry, application, studies, offer, GPS agreement, commissioning and registration. What changes is that a battery imports as well as exports. Every performance standard, study case, hold point test and registration decision has to cover charging as well as discharging, and that is where most BESS connection effort goes.
Same Process, Different Questions
The stages do not change. You still lodge a connection enquiry with the NSP, receive a response, prepare an application with R0 models, work through the NSP and AEMO assessment, negotiate the GPS, sign a connection agreement, then commission against hold points and submit R2 models. If you have not been through that sequence before, our guide to the grid connection process for solar farms walks through each stage.
What changes is the question asked at each stage. For a solar farm, the question is mostly "how does the plant behave from zero to full export?" For a battery, it is "how does the plant behave from full import to full export, at any state of charge, and through the transition between the two?" That doubles the operating envelope and adds stored energy as a constraint solar does not have.
GPS Clauses That Behave Differently for a BESS
The Generator Performance Standards list is the same for a battery as for a solar farm. The difference is that each clause has to hold across a four-quadrant operating range, and some clauses become harder or easier because of it.
| GPS area | Solar farm | BESS |
|---|---|---|
| Reactive power capability | Demonstrated from low output to rated export, often limited at night or low irradiance | Demonstrated across charge and discharge, including at or near zero active power. The PQ curve is four-quadrant, and inverter and transformer ratings must support it in both directions |
| Fault ride-through | Recover active power after the fault at the pre-fault export level | Recover to the pre-fault level whether it was importing or exporting. Behaviour at high and low state of charge must be shown, since the BMS can limit current at the extremes |
| Frequency control | Can reduce output for over-frequency. Raise response is limited by available irradiance unless headroom is held | Can respond in both directions from any operating point, including swinging from import to export. Droop settings and deadbands apply through the zero crossing |
| Voltage control | Voltage or reactive control across the export range | Same control modes, which must stay stable through the transition between charge and discharge and during fast active power swings |
| Active power control and ramping | Ramp limits on export, curtailment by setpoint | Ramp and setpoint control in both directions. Import ramp rates are often a network question as much as an AEMO one |
| Protection and runback | Export runback schemes where the network needs them | Runback or trip schemes may be needed for import as well as export, depending on which network constraint binds |
The plant controller does more work as a result. Many BESS GPS issues are not inverter capability problems. They are control interactions: a frequency response that hits a state-of-charge limit, a reactive setpoint that changes when the plant crosses zero, or a ramp limiter that fights the droop response.
Fast two-way frequency response is also where AEMO and the NSP look hardest, so droop, deadband and response time must match across the model, the GPS and the plant settings. The revenue side of that is covered in our article on how a BESS earns FCAS and arbitrage revenue.
Charging: Network Import Limits, Load-Side Obligations and Connection Charges
A battery draws power from the network, often at its full export rating and often when local load is high. That creates three issues a solar developer may not have dealt with.
Network import limits
The NSP assesses the connection for import as well as export. A connection point with plenty of export headroom may have little import capacity during evening peaks, or under certain outage conditions. The result can be an asymmetric connection, for example full export but restricted or conditional import, or an import limit tied to a runback scheme.
Test this early. A charging limit found late can change the revenue case, the duration you build, or the transformer size.
Load-side obligations
When the battery charges, the network sees a large load. That brings in the obligations that apply to customer loads, such as power factor or reactive requirements at the connection point, harmonic emission limits that apply in both operating modes, and voltage fluctuation limits for fast swings between import and export. Auxiliary load from HVAC, transformer losses and site services also has to be covered by the metering and connection arrangements.
Connection and network charges
Import changes the commercial terms. Depending on the NSP, the connection type and the jurisdiction, charging may attract network use-of-system charges or specific tariff arrangements that a generator does not face. Shared network augmentation triggered by import, and the allocation of connection asset costs, are negotiated in the offer to connect. The import assumptions in the application should match the operating strategy the project is financed on.
Studies: EMT and RMS Models for Both Modes
Every study a solar farm needs, a battery needs in both directions, plus a few solar does not have.
Steady-state
Load flow and contingency studies are run with the battery at full import and full export, against the network conditions where each is worst. Fault level contribution is assessed in both modes, and protection studies have to cover reverse power flow through the MV collector and substation.
Dynamic RMS and EMT
The PSS/E (RMS) and PSCAD (EMT) models must represent charge and discharge, the transition between them, and the BMS and state-of-charge limits that affect the response. AEMO's model acceptance tests are run across that range, so a model that only behaves well in discharge will not get through. Our article on PSS/E and PSCAD modelling for renewables explains how the two tools are used and why both are needed.
The cases that most often cause rework on BESS projects are:
BESS study cases to plan for
- Fault ride-through at full import, not just at full export
- Frequency response that crosses zero active power, with ramp and SoC limits active
- Voltage and reactive control at near-zero active power, where controllers can hunt
- Fast import-to-export swings and their effect on local voltage and flicker
- Behaviour at high and low state of charge, where the BMS limits current
- Interaction with nearby inverter-based plant in weak parts of the network
Grid-forming options
If the battery will use grid-forming inverters, decide early whether that is a commercial service, a system strength remediation measure or simply the control mode, because each leads to a different study scope; our article on grid-forming vs grid-following inverters covers the trade-offs.
Registration: Bidirectional Units and Integrated Resource Providers
Registration is where batteries have historically differed most from solar. For years a grid-scale battery was typically registered twice: once as a generating unit for discharge and once as a load for charge, each with its own DUID.
The Integrating Energy Storage Systems (IESS) reforms, which took effect in June 2024, created a framework built for storage. It introduced the concept of a bidirectional unit and a registration category, the Integrated Resource Provider, that covers plant which both imports and exports. How a specific project is classified, and how existing two-DUID batteries transition, depends on the plant configuration and on AEMO's current registration guidance. Confirm the arrangement with AEMO rather than relying on how an earlier project was set up.
The details we would check on a new BESS are:
- whether the battery will be registered as a single bidirectional unit or under an older arrangement
- how a co-located battery and solar farm will be treated behind a shared connection point
- metering arrangements for charge, discharge and auxiliary load
- the FCAS services the battery will register for, and the registration tests each one needs
On FCAS, AEMO consulted during 2026 on registration guides for BESS, wind and solar farms, with drafts published mid-year. Check the current final version before planning FCAS registration tests, as the evidence AEMO expects may differ from what an earlier project provided.
For a wider view of where registration sits in the overall program, see our guide to BESS project development in Australia.
Commissioning: State-of-Charge Planning for Hold Point Tests
Commissioning a battery uses the same hold point structure as a solar farm, but each test has to be run in both charge and discharge, and the battery's state of charge has to be planned around every test day. Each charge and discharge during testing also settles in the market, so sequencing energy movements into low-price windows is worth the effort on larger batteries. Our guide to AEMO hold point testing covers the charge and discharge tests, state-of-charge planning and R2 validation in detail.
Get BESS GPS Support
ElectraGlobe prepares GPS applications, R1 and R2 model packages, and commissioning test programs for battery and hybrid projects across the NEM.
If you have a battery connection in preparation, in assessment, or stuck on AEMO or NSP queries, see our AEMO GPS applications service, or contact our team for a quick view of where the risks sit.
Frequently Asked Questions
Does a battery need a different connection agreement from a solar farm?
The agreement follows the same NER Chapter 5 framework, but its terms reflect two-way operation. Expect import limits or conditions, performance standards that apply in both charge and discharge, and commercial terms that cover the network's import obligations. A hybrid solar and battery site may use one connection agreement covering both.
What GPS clauses apply to a BESS when charging?
The same technical areas apply in charge as in discharge: reactive capability, voltage control, frequency control, fault ride-through, active power control and power quality. The battery has to show compliance across its full import and export range, including at or near zero active power. Import-specific limits from the NSP, such as ramp rates or runback, may also be written into the agreed standards.
How long does a BESS grid connection take?
For a transmission-connected battery, enquiry to GPS approval commonly takes 18 to 36 months in our experience, similar to a solar farm. Smaller distribution connections can be quicker. Delays usually come from the NSP study queue, model rework, negotiated access standards, and charge-mode cases that were not scoped early enough.
Does a BESS have one DUID or two?
Historically, most grid-scale batteries were registered with two DUIDs, one generating unit and one load. The IESS reforms that took effect in June 2024 introduced bidirectional units, which allow storage to be treated as a single unit. How a particular project is registered depends on its configuration and AEMO's current guidance, so confirm it with AEMO early in the program.