Chapter 5A Connection Access Standards for Sub-5 MW Generators: The DNSP's Version of a GPS

A Chapter 5A connection access standard is the performance document a distribution network service provider (DNSP) agrees with an embedded generator that connects under Chapter 5A of the National Electricity Rules, typically a solar farm or battery of up to about 5 MW on an 11, 22 or 33 kV feeder. It does the job a Generator Performance Standard (GPS) does for a Chapter 5 connection: it records how the plant must behave, what it can export, and what happens when things go wrong. Different DNSPs call it different things. The content is broadly the same.

The difference from a GPS is not that the studies are lighter. It is that the document is more operational, the DNSP is the only reviewer, and the AEMO access standard framework does not apply.

Why Sub-5 MW Projects Sit Under Chapter 5A

Chapter 5A covers connections to distribution networks by retail customers and by embedded generators that are not registered participants. Most generating systems below 5 MW are exempt from registration with AEMO, so they connect under Chapter 5A through the DNSP's negotiated connection process rather than through Chapter 5 and the Schedule 5.2 access standards.

That has three practical consequences:

  • No automatic, minimum or negotiated tiers. The DNSP sets the requirements in its own connection policy and its project-specific study pack. One DNSP we have worked with asked consultants to remove references to "access standards" from Chapter 5A reports, because that is Chapter 5 language.
  • No AEMO review. The DNSP's planning, protection and power quality teams assess everything. Their technical standards and connection policies are the reference documents.
  • The NER system standards still bite. The plant must still ride through disturbances consistent with the system standards in Schedule 5.1a, and many DNSPs structure the dynamic studies around the same disturbance clauses used for larger plant (frequency disturbance, fault ride-through, and quality of electricity).

Our overview of small solar farm DNSP connections covers the commercial side of the 1 to 5 MW segment.

The Connection Process at This Scale

The sequence varies by DNSP, but the shape is consistent across the NEM.

StageWhat the DNSP providesWhat the applicant provides
Preliminary enquiryIndicative capacity, fault levels at the proposed connection point, likely augmentation, high-level network requirementsLocation, size, technology, single line diagram
Detailed enquiry or investigationA transfer capacity (thermal) assessment, augmentation options and non-contestable cost estimatesFees, more detailed plant data
ApplicationA study pack: network models, configurations, assessment criteria, protection requirements, power quality allocationSteady-state, dynamic, power quality and protection studies; the draft access standard; earthing design; SLD
Offer and agreementOffer to connect, with the access standard attachedAcceptance; the access standard is signed before the agreement is executed
CommissioningApproval of the commissioning plan, then the reportCommissioning plan, test results, final settings

Three points catch developers out:

  • The steady-state study usually gates everything else. Several DNSPs require it to be accepted before the dynamic, protection and power quality studies are reviewed. A slow steady-state loop delays the whole program.
  • Protection settings are needed early. Some DNSPs require the final protection settings report with the application, not at detailed design, because the settings are part of what the access standard records.
  • Enquiry responses expire. Validity periods of around three months are common, and the network can change in the meantime.

From study pack to offer, nine to twelve months is a realistic program on a rural feeder, and the review loops are most of it.

What the Access Standard Contains

A Chapter 5A access standard reads less like a list of performance clauses and more like an operating manual for the connection. The sections below are typical.

SectionTypical contentWhy it matters
Connection and plant dataExport and import limits at the connection point, inverter and plant controller models, firmware versions, number of unitsFirmware and parameter changes usually need DNSP endorsement before they are made
Ramp ratesLimits on how fast output may change on start-up, shutdown, and in response to price signalsProtects feeder voltage regulation; often far slower than the plant controller's default
Transformer dataVector group, earthing, tap rangeDrives the earth fault and neutral voltage protection design
Reactive power capability and controlCapability at the connection point, control mode (power factor, voltage droop or fixed Q), setpoints, droop base, limits, night-time behaviourThe main lever for keeping feeder voltage within limits
Control start-up and shutdownHow the P and Q loops enable and disableAvoids unexpected reactive output at low power
Communication fail-safeDetection times for loss of communications or bad data, and the automatic runback that followsEnsures the plant does not run uncontrolled if it cannot be curtailed
Frequency responseUsually no active power response to frequency at this scale, unless the plant offers servicesMust match the inverter settings exactly
Power quality limitsHarmonic voltage limits by order, total harmonic distortion, flicker (Pst, Plt), rapid voltage change, unbalanceAllocated by the DNSP for the connection point
Ride-throughVoltage and frequency ranges and durations the plant must stay connected forMust reconcile with the protection settings
Fault current contributionThe plant's fault contribution by fault type and whether negative-sequence current is injectedFeeds the DNSP's protection review
Special protection or runback schemesAutomatic runback for line or transformer overloads, anti-islanding requirementsOften what makes full export possible
Operational requirementsPermitted export and import in each assessed network configuration, restart approvals, curtailment acceptanceDefines how the plant runs when the network is not in its normal state
AugmentationThe specific network works the connection depends onTies the operating limits to delivered works
CommissioningPlan approval before, report approval afterThe plant can be held at zero export until the report is accepted

The operational and communications sections have no real equivalent in most Chapter 5 GPS documents. They are where a lot of review comments land, because they have to match the plant controller design, the parameter sheet and the PSCAD model exactly.

The Studies Behind It

Steady state

The DNSP supplies network models, typically for peak and light load, in each configuration it wants assessed: system normal, an alternate zone substation transformer, and supply from an adjacent feeder through a normally open point. The plant is studied at several output levels and, for a battery, while charging. Typical checks include thermal loading, voltage rise at the connection point and along the feeder, voltage fluctuation for cloud passing and for a plant trip, and interaction with tap changers and line voltage regulators. Our article on steady-state studies for embedded generators goes into the criteria and the common review comments.

Dynamic

Usually a PSCAD study on a single-machine infinite-bus equivalent, with the short-circuit ratio and X/R set from the DNSP's maximum and minimum fault levels. Faults of several depths and types, frequency excursions and rate of change of frequency, and sometimes a multiple fault sequence. One preference we see from DNSPs is that inverters hold their active and reactive current at pre-fault levels during a fault rather than boosting reactive current. That limits voltage spikes at fault inception and clearance and reduces the risk of desensitising upstream protection. It is the opposite of what AEMO generally wants at transmission level, which is a useful reminder that the two frameworks are not interchangeable.

The PSCAD model and its user guide are deliverables in their own right. Expect a parameter sheet listing every control, ramp and limit setting, and expect the DNSP to check that the sheet, the guide, the model and the access standard all say the same thing.

Power quality

A harmonic load flow with the inverter manufacturer's harmonic spectra, a flicker assessment using the inverter's certified flicker coefficient at the minimum fault level, and an unbalance check, all against the DNSP's allocation for the connection point. Some DNSPs require harmonic currents from multiple inverters to be summed arithmetically, which is conservative. See AS/NZS 61000.3.6 and 61000.3.7 allocation for how the limits are derived.

Protection

A fault study at prescribed locations, grading against the feeder's reclosers and circuit breakers, a check that the generator does not desensitise upstream protection, and anti-islanding. Protection coordination for embedded generators covers this in detail.

What DNSP Reviewers Ask Most

The same comments recur across projects and DNSPs. Most are avoidable.

Pre-Submission Checks for a Chapter 5A Package

  • One set of numbers: export, import, power factor or droop settings, ramp rates and Q limits identical across the report, summary, access standard, parameter sheet, PSCAD guide and model
  • Ramp rate units converted correctly into the plant controller's native unit and base, with a plot proving it
  • Voltage results shown before and after connection, at the correct nodes, with regulator status and tap positions stated
  • Every phase-to-phase voltage assessed separately where the feeder has single-phase regulators
  • Sign conventions stated in words (supplying or absorbing), not leading or lagging
  • Active power response to frequency disabled in the inverters and shown in the parameter sheet, if the access standard requires none
  • Fault ride-through current philosophy stated, with any current spikes at fault inception or clearance explained
  • Protection fault currents reported as seen by each upstream device, not at the fault location
  • SLD showing the connection point, every protection device and the DNSP's standard connection arrangement
  • Chapter 5 language removed; reference the access standard clauses instead

Plan the Connection Package Early

The cost of a sub-5 MW connection is often decided by a handful of steady-state results and protection constraints. Getting the plant controller design, ramp rates and protection philosophy settled before the studies start saves review rounds that a small project can ill afford.

ElectraGlobe prepares Chapter 5A study packages, access standard drafts and protection settings for embedded solar and BESS projects, and works through DNSP review. See our grid connection studies service, or contact us.

Frequently Asked Questions

Does a 5 MW solar farm need a GPS?

Not an AEMO Generator Performance Standard in the Chapter 5 sense, if it is exempt from registration and connects under Chapter 5A. The DNSP will still require a performance document, often called a connection access standard or similar, setting out export limits, reactive power control, ride-through, power quality limits and protection.

Who approves a Chapter 5A access standard?

The DNSP. AEMO does not review Chapter 5A connections of exempt embedded generators. The access standard is normally approved before the connection agreement is executed and is attached to it.

What studies does a DNSP require for a sub-5 MW connection?

Typically a steady-state study (thermal and voltage), a dynamic study in PSCAD, a power quality study, a protection study with settings, and an earthing design. The DNSP's study pack defines the network models, configurations and criteria.

Can firmware be updated after connection?

Usually only with the DNSP's endorsement. Access standards commonly record inverter and plant controller firmware versions and parameter sets, because a change can alter fault ride-through, power quality or protection behaviour.