A 5 MW solar farm in Australia almost always connects to the distribution network, so the Distribution Network Service Provider (DNSP), not AEMO, runs the connection process. Below the AEMO registration threshold most projects can be exempt from registering as a generator, which keeps the path simpler. For small scale solar farms in the 1 to 5 MW band, viability then comes down to three tests: feeder capacity, connection cost and revenue.
Why 5 MW Is a Common Size
Two things push small solar farms towards just under 5 MW: the registration framework and the capacity of distribution feeders.
The registration exemption
AEMO's registration and exemption guide has long provided a standing exemption for small generating systems with a nameplate rating below 5 MW, subject to conditions. Somewhat larger systems can apply for an exemption in some circumstances, but that is assessed case by case rather than granted automatically.
An exempt generator does not need its own AEMO participant registration, generator performance standards (GPS) or the full suite of dynamic models AEMO requires for registered plant. That removes a large part of the cost and time of a transmission-style connection.
The thresholds and conditions sit in AEMO's guidance and can change, so confirm the current position with AEMO and your DNSP before you size the plant around it.
Feeder limits
The second constraint is physical. A typical 11 kV rural feeder can often take only a few megawatts of new generation before voltage rise or thermal limits bind. 22 kV and 33 kV feeders, and connections close to a zone substation, can usually take more.
So a 5 MW farm is often the largest size that both stays inside the exemption and fits on a real feeder without a long and expensive augmentation.
The DNSP Process Step by Step
Each DNSP publishes its own embedded generation process, forms and timelines, so the detail differs between, say, Essential Energy, Energex and Powercor. The shape is broadly the same.
For an embedded generator of this size, NER chapter 5A generally governs connections to distribution networks for non-registered embedded generators, through basic, standard or negotiated connection offers. A 1 to 5 MW solar farm is almost always a negotiated connection. Where a project registers with AEMO, the chapter 5 process tends to apply instead.
| Stage | What happens | What you provide |
|---|---|---|
| Pre-application enquiry | DNSP gives indicative capacity, connection options and fees | Site location, capacity, preferred feeder or substation |
| Connection application | Formal application lodged, application fee paid | SLD, equipment data, protection concept, site plan |
| Studies and assessment | DNSP or your consultant runs network studies | Load flow, fault level, protection and PQ studies |
| Connection offer | DNSP issues technical requirements, works scope and cost | Review, negotiate, accept within the validity period |
| Design and construction | Connection works designed and built, often split between DNSP and contestable parties | Detailed design, protection settings for approval |
| Commissioning and energisation | CMP, ITPs and ITRs, witness testing, DNSP approval to export | Test results and compliance evidence |
Applications that move quickly are the ones with a complete document pack on day one. Our DNSP documents checklist lists what to prepare, and the solar farm grid connection process guide covers the larger transmission pathway for comparison.
Realistic timelines from first enquiry to connection offer commonly run from several months to over a year. The main drivers are DNSP workload, how many other generators are queued on the same feeder, and whether the studies show a need for network augmentation.
Studies Needed at This Scale
A distribution-connected solar farm does not usually need the PSCAD and PSS/E dynamic modelling package that a registered generator needs for AEMO. It does need a solid set of steady-state and protection studies, and some DNSPs will ask for more where the network is weak.
Typical Studies for a 1 to 5 MW Solar Farm
- Load flow: voltage rise at the connection point and along the feeder at full export and minimum load
- Thermal loading: conductor, transformer and switchgear ratings across seasonal cases
- Fault level: the plant's fault contribution and whether existing network equipment remains within rating
- Protection: interface protection, anti-islanding, and coordination with upstream reclosers and feeder protection
- Power quality: harmonic emissions, voltage fluctuation and unbalance against the DNSP's allocated limits
- Reactive power and voltage control: the power factor or volt-var mode the DNSP will require
Voltage rise is the study that most often decides the export limit. On a long, lightly loaded feeder, the farm may have to absorb reactive power or accept a lower export cap to keep voltages within limits.
Protection is the other common sticking point. Inverter fault current is low, so the farm can affect how existing feeder protection and reclosers see faults, and the DNSP will want that resolved before it approves settings. For the difference between steady-state and dynamic studies, see our guide to steady-state vs dynamic studies.
Costs Specific to Small Farms
The panels and inverters scale roughly with capacity. Connection costs do not, which is why they weigh more heavily on a small farm than on a 100 MW project.
| Cost item | What drives it |
|---|---|
| Connection works | Distance to a suitable feeder or zone substation, line upgrades, new reclosers or regulators |
| Network augmentation | Required where voltage rise or thermal limits are exceeded; can make or break a site |
| HV switchgear and protection | Interface protection relay, circuit breaker or recloser at the point of connection, DNSP-specified settings |
| Metering | Revenue-grade bidirectional metering, CTs and VTs, communications to the metering provider |
| SCADA and communications | Remote monitoring and, increasingly, DNSP export control signals |
| Studies and DNSP fees | Application and assessment fees, consultant studies, DNSP design review and witness testing |
| Earthing | Earth grid design and current injection testing to prove step and touch voltages |
The single biggest variable is the network augmentation the DNSP identifies after the studies. Two sites with the same panel count can differ by a large multiple in connection cost because one sits next to a zone substation and the other is 10 km down a weak 11 kV spur.
That is why we recommend a feeder screening before land is optioned.
Revenue Options
An exempt 5 MW solar farm is not an AEMO market participant, so it cannot bid into the NEM itself. The energy still has to be sold, and there are a few common routes.
Merchant via a retailer or aggregator
The usual arrangement is to sell output to a retailer, or through a party registered with AEMO to aggregate small generators, which settles the energy in the market and pays the farm a share of spot revenue. The commercial terms vary: some pay a share of the spot price, some a fixed price, some a blend.
Pure merchant exposure is risky for solar. Midday prices in the NEM are now frequently low or negative when rooftop and utility solar peak together, so a merchant small farm needs a plan for those hours, such as export curtailment at negative prices or adding storage.
Power purchase agreements
A PPA with a retailer or a commercial buyer gives a fixed price for some or all of the output. Long-term offtake is often what lenders need to finance the project.
Other factors in the revenue maths
Marginal loss factors (MLFs) apply to energy settled in the market and can materially reduce effective revenue at weak, remote connection points. Our guide to MLF and curtailment risk explains how that works. Large-scale generation certificates (LGCs) add a further, smaller stream where the farm is accredited.
Lessons From a Commissioned 5 MW Project
On a 5 MW distribution-connected solar farm we took through commissioning, the hard part was not the technology. It was the evidence the DNSP needed to sign off. The detail of that process is in our post on commissioning a 5 MW solar farm from CMP to DNSP approval.
A few lessons apply to any small farm:
- Agree protection settings early. Settings that the DNSP has not reviewed before construction are the most common cause of late changes at witness testing.
- Treat the commissioning management plan as a submission, not a formality. The DNSP approves it before testing starts, and it sets the sequence for everything else.
- Plan the earthing proof. Current injection testing needs access, equipment and dry weather, so schedule it with margin.
- Book witness testing well ahead. DNSP availability, not site readiness, often sets the energisation date.
- Keep the as-built package clean. Inconsistent drawings and ITRs mean extra review rounds and site visits.
Assess a Small Solar Farm Site
The time to test a 1 to 5 MW site is before the land is locked in and before a formal DNSP application is lodged. ElectraGlobe screens feeders, prepares connection applications and runs the load flow, fault level, protection and power quality studies DNSPs ask for, through to commissioning and approval.
See our grid connection studies service, or contact us to talk through a site.
Frequently Asked Questions
Does a 5 MW solar farm need to register with AEMO?
Generally not, if it sits below AEMO's registration threshold. AEMO's guidance has provided a standing exemption for generating systems under 5 MW nameplate, subject to conditions such as how the output is sold. Systems at or above that size need to register or apply for an exemption, so confirm the current rules with AEMO before you fix the plant size.
How long does a DNSP connection take for a small solar farm?
From first enquiry to connection offer, several months to over a year is common. The time depends on the DNSP's workload, how many other generators are queued on the same feeder, and whether the studies show augmentation is needed. Construction of the connection works and commissioning then add to that, with commissioning itself typically taking a few weeks.
What studies does a 5 MW solar farm need?
Usually load flow, thermal loading, fault level, protection coordination and power quality studies, plus a defined reactive power or voltage control mode. Full dynamic modelling for AEMO is generally not needed for an exempt generator, although some DNSPs ask for additional analysis on weak networks.
Can a small solar farm sell electricity directly?
An exempt generator cannot sell into the NEM spot market itself. It normally sells through a retailer or a registered aggregator, or under a PPA with a buyer arranged through a retailer. The right structure depends on how much price risk the owner can carry and what lenders require.