Negative Sequence Current in Unbalanced Faults: What Inverter Plants Must Do

Negative sequence current is the component of an unbalanced three-phase current that rotates in the opposite direction to normal. During an unbalanced fault, such as a phase-to-ground fault, the network voltage contains a negative sequence component, and a plant that injects negative sequence current of the right phase helps reduce the imbalance: it supports the faulted phase and limits the rise on the healthy phases. Under S5.2.5.5A of the National Electricity Rules, the automatic access standard requires inverter-based plant to have facilities to provide negative sequence current, or equivalent contributions, to oppose unbalanced voltages during a disturbance.

This matters because most faults on the network are not three-phase. Single-phase-to-ground faults are by far the most common. A plant tuned only for balanced faults is tuned for the rare case.

Sequence Components in One Paragraph

Any set of three unbalanced phase quantities can be split into three balanced sets: positive sequence (rotating normally), negative sequence (rotating backwards) and zero sequence (all three phases in step). In a healthy network, voltage is almost entirely positive sequence. During an unbalanced fault, the positive sequence voltage falls and negative sequence voltage appears. Zero sequence flows only where there is an earth path, and inverter plants usually block it through delta-connected transformer windings.

Why Positive Sequence Alone Is Not Enough

Conventional fault ride-through control measures the positive sequence voltage and injects capacitive reactive current in proportion to how far it has fallen. For a balanced fault, that is exactly right.

For an unbalanced fault, positive sequence injection raises all three phase voltages together. The faulted phase gets some support, but the healthy phases, which may already be above normal because of the fault, rise further. On networks with high zero sequence impedance, healthy phase voltages can exceed overvoltage protection thresholds, tripping the plant or neighbouring plant.

Negative sequence injection does something different. It acts against the imbalance itself: it raises the depressed phase relative to the others and lowers the healthy phases. Combined with positive sequence support, it minimises the deviation of each phase from its pre-fault value, which is exactly the control objective the Rules now define for fault response.

Fault response strategyEffect on faulted phaseEffect on healthy phasesTypical use
Positive sequence onlySome supportPushed higherOlder inverters, some distribution connections
Positive and negative sequenceBetter supportHeld closer to pre-faultModern transmission-connected plant
Balanced current (no additional injection)Limited supportLittle changeSome distribution networks, by DNSP preference

What the Rules Require

S5.2.5.5A sets out the requirements for inverter-based plant during faults:

  • Automatic access standard: facilities to supply negative sequence current or equivalent contributions to oppose unbalanced voltages, alongside the positive sequence reactive current gradients
  • Minimum access standard: the response must not contribute excessively to voltage rise on unfaulted phases during unbalanced faults
  • Performance standard records: the response to balanced and unbalanced faults and transient overvoltages, either as positive sequence reactive current against positive sequence voltage deviation and negative sequence current against negative sequence voltage deviation, or per phase, or another agreed method
  • Priority: the method of prioritising the response on reaching a current limit, including positive versus negative sequence priority

The last point is important. An inverter has a single current limit per phase. Negative sequence current adds to the current in some phases more than others, so a plant at its limit must choose how to share the available current between active, positive sequence reactive and negative sequence components. The performance standard must record that choice.

Modelling Challenges

RMS models

PSS/E and other RMS tools are positive sequence simulators. They represent unbalanced faults through equivalent impedances, but the generator models generally cannot represent negative sequence current injection by the plant. That leaves the EMT model, typically PSCAD, as the main evidence for negative sequence behaviour. OEMs commonly state that negative sequence current is available only in the EMT model. Expect the benchmarking report to explain differences between the two tools for unbalanced faults.

What to extract from EMT results

For each unbalanced fault case:

  • positive and negative sequence voltage at the connection point
  • positive and negative sequence current from the plant, on a stated base
  • the ratio of negative to positive sequence current
  • the peak voltage on each healthy phase
  • whether the plant reached its current limit, and how the current was shared

Sequence quantities are extracted with a phasor or FFT measurement block. The measurement window introduces delay, so be clear about the instant at which values are read, particularly if the response changes during the fault.

Unbalanced Fault Study Cases

  • Phase to ground, phase to phase and two phase to ground faults
  • Bolted faults and faults through impedance
  • Fault locations close to and remote from the connection point
  • Maximum and minimum SCR, with the site X/R and realistic zero sequence impedance
  • Full output and, for a BESS, full charge, with reactive power at zero and at the limits
  • Healthy phase overvoltage reported for every case

Distribution Networks Are Different

On distribution feeders, the priorities change. Some DNSPs prefer embedded inverters to hold their pre-fault current during a fault, with no additional positive or negative sequence injection. The reasons are protection related: inverter current contributes to what feeder protection measures, and an inverter that changes its current magnitude and phase during an unbalanced fault can desensitise or confuse directional and negative sequence protection elements.

DNSPs commonly ask whether the plant injects negative sequence current at all, and many embedded inverters inject positive sequence only, which makes their contribution similar for all fault types. State it clearly in the fault ride-through study and the protection study. See protection coordination for embedded generators.

Effect on Transmission Protection

At transmission level, negative sequence current from inverter plant affects protection that relies on it: negative sequence directional elements, some distance protection schemes and fault-type selection logic. Conventional protection was designed around synchronous machines, which naturally supply negative sequence current with a predictable phase. An inverter's negative sequence response is set by its control software and can differ in magnitude and angle. NSPs are increasingly asking for the negative sequence characteristic to be documented, so they can check protection performance near the plant.

Getting It Into the GPS

A clear S5.2.5.5A section on unbalanced faults should state:

  • whether the plant injects negative sequence current, and the gain or characteristic
  • how current is prioritised at the limit between active, positive sequence and negative sequence components
  • the healthy phase overvoltage performance across the study cases
  • the evidence source, usually PSCAD, with any RMS limitations explained

Our article on fault ride-through and reactive current injection covers the positive sequence requirements, and EMT vs RMS simulation explains why unbalanced behaviour needs EMT.

Get Unbalanced Fault Behaviour Right

ElectraGlobe studies unbalanced fault behaviour in PSCAD, works with OEMs on sequence current settings, and documents the response in GPS proposals. See our steady-state and dynamic studies service, or contact us.

Frequently Asked Questions

What is negative sequence current?

It is the component of an unbalanced three-phase current that rotates in the opposite direction to normal. It appears during unbalanced faults, and a plant that injects it with the right phase helps reduce voltage imbalance.

Do inverters have to inject negative sequence current in the NEM?

Under the automatic access standard in S5.2.5.5A, inverter-based plant must have facilities to provide negative sequence current or equivalent contributions to oppose unbalanced voltages. The minimum access standard requires that the response does not contribute excessively to voltage rise on unfaulted phases.

Can PSS/E model negative sequence injection?

Generally not in the generator models used for connection studies, because PSS/E is a positive sequence RMS tool. Negative sequence behaviour is normally demonstrated with the EMT model in PSCAD.

Why does negative sequence current matter for protection?

Some protection elements, such as negative sequence directional elements, rely on the negative sequence current supplied by sources during a fault. An inverter's response is set by software and can differ from a synchronous machine's, so NSPs want it documented and checked.