Owners add a battery to a solar farm to recover energy lost to curtailment and to move midday output into evening hours, when prices are usually higher. There are two ways to do it: AC coupling, with the battery on its own inverters, or DC coupling, behind the existing PV inverters. Either way, the retrofit alters a connected generating system, so it reopens the connection agreement, the performance standards and the registration.
The battery itself is rarely the hard part. The connection, the models and the site's electrical limits usually decide whether a retrofit is worth doing.
Why Now: Negative Prices and Curtailment on Operating Plants
Most solar farms in the NEM were financed on a model where midday energy had value. That assumption has worn thin. A RenewEconomy analysis reported about 7.9 TWh of utility solar and wind curtailment in the NEM in the year to 10 April 2026, around 82% of it during negative prices. For September 2026, Modo Energy reported an average NEM solar capture price of about $17/MWh and curtailment of roughly 22% of available solar output, with the most negative midday prices in South Australia and Victoria. Our article on solar curtailment in the NEM sets out the numbers and the other fixes.
Certificate revenue has also fallen a long way from its 2022 levels, removing much of the cushion that once let a plant generate through moderately negative prices.
A battery addresses the economic part of that problem directly: energy that would be spilled at midday is stored and sold later. It does less for network curtailment if the same constraint also binds in the evening. We explain the difference between the two, and how they interact with loss factors, in our guide to MLF and curtailment risk. Knowing your split is the first step in any retrofit case.
AC vs DC Coupling for a Retrofit
The new-build case for each architecture is covered in our article on hybrid solar and BESS in Australia. For a retrofit, the existing plant narrows the choice.
| Consideration | AC-coupled retrofit | DC-coupled retrofit |
|---|---|---|
| New equipment | Battery, own PCS inverters, MV transformers, MV switchgear | Battery and DC/DC converters at each PV inverter block |
| Where it connects | MV collector bus or the site substation | DC side of the existing PV inverters |
| Conversion losses | Battery energy is converted twice more (AC to DC to AC) | Solar energy can charge the battery without an extra AC conversion |
| Captures clipped PV energy | No | Yes, if the DC/AC ratio produces material clipping |
| Grid charging | Yes | Usually limited, depends on the inverter |
| Export capacity at the connection point | Solar plus battery can exceed the current limit, so the limit is often reviewed | Unchanged, since the PV inverters cap the output |
| Metering | Battery often separately metered, more registration options | Battery energy sits behind PV inverter metering |
| What the existing inverters must allow | Nothing, they are unchanged | DC-coupled storage support, firmware and warranty acceptance from the OEM |
| Revenue flexibility | Arbitrage, FCAS, contracts and grid charging | Mostly shifting solar energy |
In practice, the existing inverters often decide the question. Many central and string inverters installed in the late 2010s were never designed for DC-coupled storage, and the OEM may not support it, or may support it only with a firmware upgrade and revised warranty terms. If that is the case, AC coupling is the only option.
AC coupling is more flexible and is the usual choice where the battery should earn from grid charging and frequency services as well as solar shifting. DC coupling suits plants with significant clipping, compatible inverters and a connection where reopening the export limit would be slow or expensive.
Connection and GPS: What a Retrofit Reopens
Is It a Modification?
Adding a battery changes the plant's capability: it can now absorb power, inject power at times it previously could not, and respond differently to faults and frequency events. In the NER, a proposal to alter a connected generating system follows its own process, commonly referred to by its clause number, 5.3.9. The NSP and AEMO assess what the alteration affects and which performance standards need to be revisited.
The exact pathway depends on the configuration, the size of the battery relative to the plant, whether the export limit changes and the version of the rules that applies. Confirm it with the NSP and AEMO before committing to a design.
Which Access Standards Are Reopened
Not every clause of the existing performance standard is renegotiated, but a retrofit usually touches several. Typical ones include:
- Reactive power capability and voltage control, because the plant's capability curve and its control strategy at the connection point change.
- Active power control and ramp rates, because the battery can change output much faster than the PV plant.
- Frequency response, including the plant's droop behaviour and whether the battery provides fast response.
- Fault ride-through behaviour, since the battery PCS adds another inverter fleet with its own response to faults.
- Power quality, since new inverters and transformers change harmonic emissions at the connection point.
The negotiated levels in your existing Generator Performance Standards are the starting point. A good outcome keeps them largely intact and adds what the battery needs.
New Models and Studies
The plant needs updated RMS and EMT models that represent the PV inverters, the battery PCS and the plant controller together. Those models then go through the usual studies: load flow, fault level, dynamic and, where the network is weak, system strength assessment. We describe how those models are built and reviewed in our article on PSS/E and PSCAD modelling.
The plant controller is most often underestimated. It must coordinate two fleets at one connection point, hold the export limit, follow dispatch and meet the voltage control standard, and its model must match what is installed.
Registration and Metering
Since the integrating energy storage systems (IESS) rule changes took effect in June 2024, the NEM has a registration framework designed for storage and hybrid sites. In broad terms, a battery is treated as a bidirectional unit, and a site combining generation and storage can be registered under the integrated resource provider category. The details of how an existing solar farm's registration changes, and whether the battery becomes its own unit, depend on the configuration and are worked out with AEMO.
Metering follows the same logic. An AC-coupled battery is often metered separately so its import and export can be settled on their own. A DC-coupled battery sits behind the PV inverters, so the site may continue to present as one generating unit at the connection point. Check that the metering installation can record import, which many solar-only sites were not set up for, and that auxiliary load is metered correctly.
Site Practicalities
A retrofit has to fit inside a plant that was not designed for it. These items usually decide the cost:
- Space. Battery enclosures, PCS skids and transformers need a pad with access for cranes and maintenance, and with clearances for fire separation. Land inside the existing fence is often tighter than expected.
- Earthing. The new equipment has to be bonded into the existing earth grid, and the earthing study updated for the new fault paths and step and touch potentials.
- MV switchboard capacity. An AC-coupled battery needs spare bays or a new switchboard section. Check the busbar and fault ratings, not just the number of free panels.
- Transformer rating. The main transformer was sized for PV export. If the battery can push the site above that, either the export is capped by the controller or the transformer limits the size of the battery.
- Protection. New feeders, new fault contributions and reverse power flow during charging all need protection settings reviewed, including at the NSP's end.
- Fire separation and planning. Battery enclosures need separation distances and a fire risk assessment, and the development approval may need modifying to add them.
Revenue Logic: What to Model
The revenue case for a retrofit rests on three streams, and the model should value each separately.
- Shifting curtailed energy. Energy the plant would have spilled during negative prices is stored and sold later. Its value is the evening price, adjusted for loss factors, less round-trip losses. This is the stream that justifies most retrofits.
- Arbitrage. An AC-coupled battery can also charge from the grid when prices are low and discharge when they are high, independent of solar.
- FCAS and contracts. Frequency services and cap or firming contracts can add revenue, but FCAS prices have fallen as more batteries have entered the market. Our article on how BESS make money in Australia covers the stack.
A credible model works from historical five-minute prices and plant data, not daily averages. It should include round-trip efficiency, auxiliary load, degradation and augmentation, the export limit when solar and battery run together, and a capture-rate haircut, because no operator achieves perfect foresight. It should also test sensitivity to future MLFs and to a changing curtailment profile.
We do not quote typical uplift figures, because they depend almost entirely on the plant's own curtailment history, its region and its connection limits. Two plants of the same size can produce very different answers.
Retrofit Feasibility Checklist
Before You Commit to a BESS Retrofit
- Curtailment split: how much lost energy is economic and how much is network-driven
- Inverter compatibility: whether the existing PV inverters and OEM support DC coupling
- Connection limit: whether solar and battery can export together, or the limit must change
- Existing GPS: which negotiated standards are likely to be reopened
- Electrical headroom: transformer rating, MV switchboard bays, fault levels and protection
- Space and approvals: pad area, fire separation and whether the development approval needs modifying
- Registration and metering: how the site will be registered and settled after the change
- Revenue model: interval-level model with losses, degradation and a capture-rate haircut
- Program: the connection, model and approval path, which is usually longer than battery delivery
Assess a Retrofit With ElectraGlobe
ElectraGlobe works with owners of operating solar farms to test whether a battery retrofit stacks up, from the curtailment analysis and coupling choice through to the connection, models and amended performance standards. Our utility-scale solar and BESS engineering team covers the design, and our AEMO GPS applications team carries the change through the NSP and AEMO.
If your plant is spilling more energy than its financial model assumed, contact our team and we can tell you quickly whether a retrofit is worth a closer look.
Frequently Asked Questions
Does adding a battery to a solar farm need a new connection agreement?
Usually the existing connection agreement is amended rather than replaced, because the change is treated as an alteration to a connected generating system. The extent of the amendment depends on whether the export limit changes and which performance standards are affected. Confirm the pathway with the NSP and AEMO before design is fixed.
Is AC or DC coupling better for a retrofit?
It depends mostly on the existing inverters and the connection. AC coupling works with any inverter, allows grid charging and FCAS, but often needs the export limit reviewed. DC coupling captures clipped energy and can leave the export limit unchanged, but only works where the PV inverters and their OEM support it.
Will adding a BESS change my MLF?
The loss factor applies at the connection point and AEMO recalculates it every year, so the battery does not change it directly. Over time, a site that exports more in the evening and less at midday changes the flows AEMO models, which can affect future values. Loss factors for the stored and discharged energy should be modelled as part of the revenue case.
How long does a BESS retrofit take?
The construction itself can be relatively short, but the connection change, updated models, studies and approvals usually set the program. It is common for the regulatory path to take longer than battery procurement and installation. Starting the NSP and AEMO conversation early is the most effective way to shorten it.