The 2026 ISP for Developers: What Changed and What It Means for Connecting Projects

AEMO published the final 2026 Integrated System Plan on 25 June 2026. In short, the 2026 ISP keeps the same least-cost path of renewables, transmission, storage and gas backup, but compared with 2024 it plans more solar, less wind, more batteries and about 1,435 km less new transmission overall. For developers, the changes that matter are where batteries now do the work transmission used to do, which projects became actionable, and how much generation AEMO expects to be spilled or curtailed.

Below is an engineer's reading of the parts that affect siting, storage and connections. Figures are from the final ISP, Step Change scenario, unless noted.

The 2026 ISP in Numbers

Item2026 ISP figureNotes
Utility-scale wind and solar by 2050Almost 120 GWAbout five times current levels
Grid-scale solar31 GW by 2030, 64 GW by 2050More than in the 2024 ISP
Onshore wind30 GW by 2030, 44 GW by 2050Total 2050 wind down 23% from 69 GW in 2024
Offshore wind9 GW by 2040None further to 2050
Shallow and medium storage (under 12 hours)About 33 GW by 2030, 35 GW by 2050Mostly batteries. Shallow is under 4 hours, medium 4 to 12 hours
Deep storage (12 hours or more)5 GW by 2050New pumped hydro, on top of 7 GW existing hydro
Flexible gas17 GW by 2050Backup and peak supply
Rooftop and small-scale solar87 GW by 2050With 35 GW of consumer batteries
New transmissionAbout 6,000 km by 2050Extends the existing 44,000 km network by almost 14%
CoalTwo-thirds of remaining capacity retires by 2035All projected to retire by 2049
Renewable share82% by 2030, 98% by 205082% is the federal target, modelled as a policy input. About 75% by 2030 on current delivery trends. Around 45% in 2025
Grid-scale renewables spilled or curtailedAbout 15% by 2050Treated as the efficient level, not a failure
Net market benefit of ODP transmission$28 billionWeighted across three scenarios
Investment to 2050$106 billionGeneration, storage, firming and network, in today's dollars

The 82% figure is the federal target, which AEMO builds into its scenarios as a policy input rather than a forecast. AEMO also notes that current delivery trends point to about 75% renewable generation by 2030, a gap we cover in our article on Australia's 2030 renewable energy target.

Two numbers stand out. Grid-scale storage progressing through AEMO's connections process rose from 3 GW in September 2022 to 45 GW at the start of 2026, well above the 33 GW of shallow and medium storage AEMO says is needed by 2030. And AEMO plans for roughly one in seven megawatt-hours of grid-scale renewable output to be spilled or curtailed by 2050.

What Changed Since the 2024 ISP

The direction has not changed. The mix and the transmission map have.

More Solar, Less Wind

AEMO now projects more grid-scale solar than it did in 2024, at 125 TWh a year by 2050 compared with 119 TWh. The reasons it gives are lower solar costs relative to wind, and the build-out of anticipated batteries, which suit solar well. Total wind capacity in 2050 falls 23% from 69 GW. Wind's share of generation falls by less, because newer turbines are more efficient and some sites are now modelled with stronger wind.

Batteries Replacing Some Transmission

This is the change developers should read most closely. AEMO lists the main reasons projects were reclassified, and several of them come down to storage and location:

  • Well-located batteries reduce the benefit of some transmission projects, because both add reliability and make better use of renewable output.
  • Generation built close to demand, typically solar, reduces the need for transmission. Generation in remote areas such as South West NSW, typically wind, increases it.
  • Some transmission connections to generation have been replaced by cheaper options in the distribution network.
  • Higher transmission cost estimates have pushed some projects below a net benefit.

About 1,680 km of potential lines are no longer needed. Scope increases on other projects offset part of that, which is why the net reduction quoted above is about 1,435 km.

Costs and Financing Assumptions

The capital cost of the 2026 optimal development path (ODP) is 7% higher than in 2024, after adjusting for inflation and other factors. Solar and battery costs are lower. Wind and transmission costs are higher. AEMO also changed its assumed weighted average cost of capital (WACC) for different infrastructure types after consulting on the 2025 Inputs, Assumptions and Scenarios Report (IASR).

Actionable Projects and the Non-Network Options Call

An actionable project is a transmission project the ISP says should progress now. Under the ISP framework, that means the network service provider starts or continues a regulatory investment test for transmission (RIT-T). Some projects instead go through state legislation in NSW, Queensland or Victoria. The ODP includes eight committed and anticipated projects adding about 3,500 km over the next eight years, and twelve actionable projects adding about 1,660 km over the next 12 years. The table shows selected projects, not the full list.

StatusProjectTiming advised by proponent (full capacity)
Committed or anticipatedProject EnergyConnect Stage 2November 2027
Committed or anticipatedHumeLinkDecember 2027
Committed or anticipatedCentral-West Orana REZ Network InfrastructureDecember 2028
Committed or anticipatedProject Marinus Stage 1December 2030
Already actionableVNI West (NSW-VIC)November 2031
Already actionableSydney Ring North (Hunter Transmission Project)November 2029
Newly actionableTasmania REZ ExpansionJuly 2030
Newly actionableCentral to North Queensland Reinforcement (Stage 1)July 2031
Newly actionableBrisbane Area 275 kV ReinforcementJune 2032
Newly actionableCentral-West Orana REZ ExpansionMarch 2033

Seven projects are newly actionable. Five were future projects in 2024 that have moved into the actionable window: Western Victoria Reinforcement, Tasmania REZ Expansion, Central to North Queensland Reinforcement (Stage 1), Gippsland Offshore Wind Transmission and Central-West Orana REZ Expansion. Two are new: a switching station near Wondalga on HumeLink, and the Brisbane Area 275 kV Reinforcement. QNI Connect has moved back to a future project.

For three newly actionable projects under the ISP framework, AEMO called for non-network options, with submissions due on 17 September 2026. The three projects are the Brisbane Area 275 kV Reinforcement, Central to North Queensland Reinforcement (Stage 1) and the Tasmania REZ Expansion. That deadline has passed, but submissions feed the proponent's Project Assessment Draft Report, due around mid-2028. A battery developer near one of these corridors should track the RIT-T, because storage that relieves the same constraint is what the process is meant to test.

Transmission Timing and Project Risk

The ISP is a plan, not a delivery guarantee. A project that depends on a new line inherits that line's program risk.

HumeLink

HumeLink is now committed, with in-service and full capacity both advised for December 2027. It has been open to connection enquiries for renewable and storage projects. The new switching station near Wondalga, advised for April 2031, is meant to improve transfer from southern NSW to Bannaby.

VNI West

VNI West remains actionable but later than earlier plans. Proponents advise the South West REZ component for August 2029. The NSW-VIC link is advised for in-service in November 2030 and full capacity in November 2031.

Project Marinus

Marinus has been split into two projects. Stage 1 is anticipated, with full capacity advised for December 2030. Stage 2 remains actionable, with full capacity advised for December 2034.

What a Delay Does to Your Project

A project that assumes a line is in service when it is not faces three effects:

  • Loss factors. Marginal loss factors get worse when more generation exports through an unchanged network. A new line can lift MLFs in a congested area, so a delay holds them down for longer. We cover the mechanics in understanding MLF and curtailment risk.
  • Network curtailment. Constraint equations bind more often until the new capacity arrives, so output is limited in exactly the hours the plant is producing most.
  • Connection terms. NSPs may limit output, delay full output or tie a hold point to network works until the line is in service.

AEMO's own delayed-delivery case found the transmission becomes more valuable, not less. For a developer, the lesson is to model a case where the relevant line is a year or two late and see whether the project still works.

What the 2026 ISP Means for Siting, Storage and Connection Strategy

Siting

The ISP does not approve or refuse sites, but it shows where AEMO expects capacity and network. Our practical reading:

  • Solar near load is favoured. AEMO's reasoning is that solar close to demand needs less transmission. Sites near strong 132 kV or 275/330 kV networks close to load centres, or near large new industrial load, are worth a second look.
  • REZ access is a real asset. In NSW, EnergyCo's Central-West Orana REZ access rights total 7.15 GW, and access fees apply from the start of commissioning. Inside a REZ you trade a fee and a scheme process for more certain network capacity.
  • Congested corridors stay congested until the line arrives. If your site depends on a project advised for 2030 or later, price that in.

See also our solar farm site selection guide.

Storage Duration

AEMO's 35 GW of shallow and medium storage covers both intra-day bands: shallow (under four hours) and medium (four to 12 hours). Deep storage, 12 hours or more, is a separate 5 GW. With 45 GW of storage in the connections pipeline against a 33 GW need in 2030, any battery competing only on arbitrage in a crowded node faces competition, whatever its duration. Location, duration matched to the local price shape, and a network service role are what will separate projects. A battery that relieves a known constraint, or pairs with solar that is otherwise spilling, has a clearer revenue case than one that only does arbitrage. For how co-location works in practice, see utility solar and BESS.

Connection Strategy

  • Expect curtailment and design for it. If AEMO plans for about 15% of grid-scale renewable output to be spilled or curtailed by 2050, a financial model with no curtailment is not credible. Hybrid design, DC/AC ratio and export limits should be set with that in mind.
  • Plan studies around network change. Connection studies are run against a future network. Know which committed and actionable projects your NSP is assuming, and when.
  • Look at the distribution network. AEMO now treats distribution as an alternative to some transmission. For projects of roughly 5 to 30 MW, a DNSP connection may be the faster route.

For the wider market context, see our explainers on the National Electricity Market and renewable energy in Australia, and our guide to grid connection for solar farms.

Talk to Us About Project Siting

ElectraGlobe's utility-scale solar and BESS engineering team helps developers turn plans like the ISP into site decisions. That means screening connection points against planned network changes, sizing storage for the constraint it actually faces, and setting up the connection studies to suit.

If you are weighing up a site or a storage duration in light of the 2026 ISP, contact our team for a quick read on the connection risk.

Frequently Asked Questions

What is AEMO's Integrated System Plan?

The ISP is AEMO's long-term plan for the National Electricity Market. It sets out the least-cost mix and timing of generation, storage and transmission to 2050. It identifies an optimal development path and the transmission projects that should progress now. AEMO prepares it as the National Transmission Planner.

When is the next ISP due?

The ISP is published every two years, so the next full plan is the 2028 ISP. The AEMC is also reviewing the long-term planning frameworks, including a statutory review of the ISP, which may affect later editions.

What are ISP actionable projects?

Actionable projects are the transmission projects the ISP says should progress now to deliver the optimal development path. Under the ISP framework, the network service provider must carry them through a RIT-T. Some are instead delivered under state legislation in NSW, Queensland or Victoria. The 2026 ISP has twelve actionable projects, seven of them newly actionable.

Does the ISP decide where solar farms can be built?

No. The ISP models where capacity is likely to be efficient, but private developers decide where to build. The ISP is still a useful guide to where network capacity is likely to grow and where it will stay tight.