System Strength Charges Explained: Pay the TNSP or Self-Remediate?

Under the NEM's new system strength framework, transmission network service providers (TNSPs) now plan and supply system strength for their regions. A new solar, wind or BESS connection either pays the TNSP's system strength charge or self-remediates its own impact on the network. Which path is cheaper depends on the project and on the network it connects to, and the choice has both a commercial side and an engineering side.

What Changed: From "Do No Harm" to a Planned Service

System strength is a measure of how well the network holds its voltage waveform steady, especially during and after a fault. In practice it is closely tied to the available fault current at a location. Synchronous machines such as coal, gas and hydro units supply a lot of it. Grid-following inverters supply very little, and they also need a reasonably strong grid to stay stable themselves.

Under the old arrangement, each new connection was assessed for its impact on system strength, and if it made things worse it had to fix that impact before it could connect. This "do no harm" approach worked when connections were scattered. It worked badly once dozens of inverter-based projects began crowding into the same parts of the network. Each project studied its impact against a moving baseline, and the remedies were piecemeal.

The replacement framework came out of the AEMC's system strength rule changes. The pay-or-remediate choice for connecting inverter-based plant has applied since 15 March 2023, and TNSPs, as System Strength Service Providers, became responsible for meeting the new standard from 2 December 2025. The core changes are:

  • TNSPs plan system strength centrally. Each system strength service provider must meet a standard at defined nodes on its network, based on AEMO's forecasts of minimum fault levels and the inverter-based plant expected to connect.
  • Connecting plant has a choice. A new connection subject to the framework can pay a charge that funds the TNSP's central solution, or it can self-remediate so that it does not draw on that service.
  • The assessment is still technical. Either way, the plant's impact still has to be assessed.

For a broader picture of why system strength became a bottleneck in the first place, see our overview of grid integration challenges for renewable energy in Australia.

How the System Strength Charge Is Worked Out, in Principle

The exact method, terms and prices are set out in each TNSP's published system strength pricing documents and in AEMO's guidance. They differ in detail between TNSPs and are revised over time, so treat the following as the shape of the calculation rather than a formula to price a project from.

In broad terms, the charge combines three things:

  • A quantity for the plant. This reflects how much system strength the connection needs from the network. It scales with the size of the plant, and it is reduced if the plant can operate stably at a lower short-circuit ratio than the reference level, because a more robust plant draws less from the system.
  • A unit price. The TNSP publishes a price per unit of system strength, which reflects the cost of the central solution it has planned, whether that is synchronous condensers, contracted generators, grid-forming batteries or a mix.
  • A locational element. Location matters. A project at an electrically weak node, a long way from synchronous sources, generally attracts more cost than the same project close to a strong part of the network.

Three practical consequences follow.

First, plant capability changes the bill. Inverters that remain stable at a lower short-circuit ratio reduce the quantity the plant is charged for. That is an equipment selection and tuning question, and it can be tested in studies before the inverter is locked in.

Second, the charge is a recurring cost, not a one-off. It belongs in the financial model alongside transmission use of system charges and the marginal loss factor (MLF) haircut, not in the capex line.

Third, the price can move. TNSP unit prices are revised as their plans and costs change. A project that pays the charge is exposed to that; a project that self-remediates swaps price risk for capex and performance risk.

Self-Remediation: The Options and What It Takes to Prove Them

Self-remediation means the project provides, or offsets, the system strength it would otherwise draw from the TNSP. There are four broad routes, and they are often combined.

Synchronous condensers

A synchronous condenser is a synchronous machine with no prime mover. It spins on the grid and supplies fault current and inertia. It is proven, understood by every NSP, and modelled the same way as a conventional generator. The downsides are cost, lead time, losses, maintenance and site footprint. For a single mid-sized solar farm a dedicated syncon is rarely economic, but it can make sense for a large hub or a cluster of projects under common ownership.

Grid-forming BESS

A grid-forming inverter sets its own voltage and frequency reference rather than following the grid's. It can stabilise a weak network and contribute to system strength in ways a grid-following inverter cannot. If the project already includes a co-located battery, specifying it as grid-forming is often the lowest-cost route to remediation. The open question is how much credit it receives, which we return to below.

Inverter tuning and plant capability

Sometimes the cheapest remedy is in the control settings. Retuning phase-locked loop and current controller parameters can let a plant operate stably at a lower short-circuit ratio. That reduces both its own vulnerability and the quantity used to work out the charge. This route needs the OEM's cooperation and validated models, and it does not suit every plant.

Network or connection design changes

Moving the connection point, connecting at a higher voltage, or sharing a connection with a synchronous or grid-forming asset can change the outcome. These are concept-stage decisions.

What the assessment involves

None of these options counts until it is demonstrated. Self-remediation has to be shown through system strength assessment to the satisfaction of the NSP and AEMO. Our guide to the system strength impact assessment covers the process in more detail. That usually means:

  • Screening with short-circuit ratio and available fault level calculations across credible network conditions, including minimum fault level and planned outages.
  • Detailed electromagnetic transient (EMT) studies in PSCAD of the plant and nearby inverter-based plant, to check for control instability and adverse interactions.
  • Positive-sequence studies in PSS/E for the wider network response.
  • Model packages and performance that line up with the generator performance standards being negotiated at the same time.

The study effort is material, and it runs in parallel with the GPS work. Our guide to PSS/E and PSCAD modelling for renewables in Australia covers what those models must contain and why AEMO needs both.

A Decision Framework: Pay or Remediate?

There is no universal answer. The useful question is which factors push a specific project one way or the other. In our experience on connection studies, these five do most of the work.

FactorLeans towards paying the chargeLeans towards self-remediation
Project sizeSmall to mid-sized plant, where a remedy's fixed costs are hard to spreadLarge plant or multi-stage hub, where remedy costs are spread over more MW
Location and existing fault levelStrong node, close to synchronous generation or a planned TNSP solutionWeak node, high locational cost, or a long way from the TNSP's planned assets
Co-located BESSNo battery in scope, or a battery with no grid-forming optionBattery already in scope, and grid-forming capability available at modest extra cost
Inverter capabilityPlant cannot reach a materially lower short-circuit ratio with tuningPlant can be tuned or specified to operate stably at a low short-circuit ratio
TimingTNSP solution is in place or close, and the project needs certainty quicklyTNSP solution is years away, or the price outlook is uncertain and the owner prefers capex certainty

A few observations on using the table:

  • Run the numbers both ways. Compare the present value of the charge over the asset life, with sensitivities on unit price, against the capex, opex and study cost of the remedy. Include the cost of a remedy that underperforms.
  • Do it at concept stage. The decision affects inverter selection, whether the BESS is grid-forming, single line diagram design and connection point. By the time the connection offer arrives, most of the cheap options are gone.
  • Do not count on a credit you cannot model. A grid-forming battery that is not yet in the study models is a hope, not a remedy.

Where TNSP Plans Stand in 2026

The TNSPs' central solutions are still being procured and built. Two developments matter most for the decision.

Transgrid's mix of syncons and grid-forming batteries

Transgrid's July 2025 plan for New South Wales, set out in the Project Assessment Conclusions Report for its regulatory investment test, proposed ten synchronous condensers, about 5 GW of grid-forming batteries and 650 MW of existing generators running in condenser mode. Its July 2026 update, released for consultation, cut the synchronous condensers needed in later stages of the program from ten to eight, with the Phase 1 units proceeding as planned, and opened a pathway for grid-forming batteries to form part of the minimum-level portfolio. It signals that TNSPs see grid-forming batteries as part of the solution. Projects in NSW should still check the published plan and pricing for the node they connect to, as the details drive the locational outcome.

AEMO's caution on grid-forming for minimum fault level

AEMO has been more careful. Its 2026 General Power System Risk Review, released in July 2026, found that grid-forming batteries have not yet been confirmed as able to supply the fault current needed for minimum system strength, the level that underpins protection operation, and AEMO is setting up a fault-current trial to build that evidence.

In practice, a developer counting on a grid-forming battery to self-remediate should expect to prove its contribution in EMT studies rather than be credited like a synchronous machine; our comparison of grid-forming and grid-following inverters explains why.

Get a System Strength Assessment Before You Commit

The pay-or-remediate decision is usually made too late, after the inverter is chosen and the connection offer has arrived. Made at concept stage, it can still change the inverter, the BESS configuration and the connection point.

ElectraGlobe's power systems team carries out short-circuit ratio screening, PSS/E and PSCAD studies, and system strength assessments for solar, wind and BESS connections across the NEM. We can model both paths for your project and show you where the real cost sits. See our steady-state and dynamic studies service, or contact us to discuss your connection.

Frequently Asked Questions

Who pays for system strength in the NEM?

Under the current framework, the TNSP plans and procures system strength for its region. Part of that cost is recovered from customers through network charges, and new inverter-based connections that draw on the service pay a system strength charge. A connecting project can avoid the charge by self-remediating, provided it can demonstrate that remedy through assessment.

Can a grid-forming battery meet system strength obligations?

It can contribute, and TNSPs such as Transgrid are planning around grid-forming batteries as part of their solutions. AEMO's 2026 General Power System Risk Review found, however, that grid-forming batteries are not yet confirmed as able to supply the fault current needed for minimum system strength, and AEMO is setting up a trial to test this. A project relying on a grid-forming BESS should expect to prove its contribution in detailed EMT studies.

Does the system strength charge apply to DNSP-connected projects?

It can, depending on the size of the project and how it is registered. System strength is planned at transmission level, but large distribution-connected generators can still affect it and may be assessed under the framework. Ask the DNSP early how system strength will be treated for your connection, because the answer affects the study scope and the financial model.

How is system strength measured?

It is usually expressed through available fault level at a location, in MVA, and through the short-circuit ratio, which compares the fault level with the rating of the connecting plant. A low ratio indicates a weak connection point. Screening uses these metrics, but a weak-grid connection normally needs detailed EMT studies to confirm the plant will remain stable.