A system strength impact assessment (SSIA) tests two things for a new solar, wind or BESS connection: whether the plant will stay stable at its connection point, and whether it makes the network weaker for everyone else. It runs in two stages, a screening calculation based on short-circuit ratio and fault level, then, where screening flags a risk, a full electromagnetic transient (EMT) study. The outcome is either a clean result, a set of plant changes, or a remedy the project has to fund.
System Strength in Plain Terms
System strength describes how well the network holds its voltage waveform steady, particularly during and just after a fault. The usual proxy is fault level: the current, expressed in MVA, that flows into a three-phase fault at a given point. A high fault level means a stiff network that barely moves when something switches or trips. A low one means the voltage swings further and recovers more slowly.
Synchronous machines (coal, gas, hydro and synchronous condensers) supply large fault currents because their rotating fields physically resist voltage change. Grid-following inverters supply a limited, controlled current, not much more than their rating, and rely on the network voltage as their reference.
That reliance is the core problem. A grid-following inverter uses a phase-locked loop (PLL) to track the grid voltage. On a stiff network that voltage is steady. On a weak network the inverter's own output moves the voltage it is tracking, the controls chase themselves, and the result can be sustained oscillation, poor fault recovery or a trip.
Short-circuit ratio
The short-circuit ratio (SCR) puts a number on this. It is the fault level at the connection point divided by the rated capacity of the connecting plant:
- SCR = fault level (MVA) / plant rating (MW)
A 100 MW solar farm at a point with 500 MVA of fault level has an SCR of 5. The same plant at a 200 MVA point has an SCR of 2. As a broad rule of thumb, an SCR above about 3 is regarded as reasonably strong for grid-following plant, and below about 3 is where weak-grid behaviour starts to need careful study. Each inverter model has its own minimum SCR, set by the manufacturer and tested in its models, and that figure matters more than any general threshold.
Screening: The First Pass
Screening is a desktop calculation that shows whether a full assessment is likely to be needed. The specific method, metrics and thresholds are set by AEMO's system strength guidance and by the connecting network service provider, and the terminology has been revised alongside the AEMC's system strength framework (with TNSPs responsible for the new standard from 2 December 2025). Check the current version with the NSP at the start of any study rather than relying on an older guideline.
In practice, screening usually covers:
- Fault level at the connection point under system normal conditions and under credible outages, including the minimum fault level case. The minimum case drives the result, not the typical one.
- SCR for the plant alone, compared with the inverter's stated minimum.
- A combined measure for nearby plant. Where several inverter-based plants sit electrically close together, they share the same fault level. Metrics such as a weighted SCR account for that, and they often show a much weaker picture than the plant's own SCR.
- Future network conditions. Committed generators, planned retirements of synchronous plant and committed network changes all move fault levels over the life of the asset.
Comfortable margins across all credible conditions may end the assessment there or reduce its scope. Thin margins, or a weak area shared with other inverter-based plant, lead to a full assessment.
Full Assessment: Wide-Area EMT Studies
A full assessment is built in an EMT tool, usually PSCAD. EMT simulation models actual voltage and current waveforms at microsecond time steps, including the inverter's control loops, PLL and protection logic, which is the only way to see the control interactions behind weak-grid instability. Positive-sequence RMS tools such as PSS/E average those dynamics out. Our overview of PSS/E and PSCAD modelling for renewables in Australia covers how the two model types fit together.
What the model contains
- The plant, using the OEM's validated PSCAD model of the inverter, configured with the actual control settings, plus collector network, transformers, reactive plant and the power plant controller.
- The wider network, as a reduced wide-area model supplied or approved by the NSP or AEMO. It extends far enough to capture the electrically close part of the system and its synchronous sources.
- Neighbouring inverter-based plant, each with its own validated EMT model. This is often the slowest part to assemble, because those models belong to other owners and are released through the NSP.
What the studies test
The scenario set varies by NSP, but a typical full assessment runs:
- Balanced and unbalanced faults at and near the connection point, with fault ride-through and post-fault recovery checked against the required performance.
- Contingencies that reduce fault level, including the planned outage cases identified in screening.
- Voltage and active power setpoint changes, to look for poorly damped or sustained oscillations.
- Operation at minimum fault level with all nearby plant at full output, which is often the hardest case.
- A comparison with and without the new plant, to show whether it degrades the stability of existing generators nearby.
That last test makes it an impact assessment: a plant can be stable itself and still push a neighbour over its limit.
Why it takes time
Model quality drives the schedule. OEM models must be the right version with as-designed settings, the NSP's wide-area case must be current, and neighbour models must initialise and run together, which often exposes PSCAD version or compiled-model compatibility problems. Most of the elapsed time typically goes on assembling and debugging the model set, not running cases.
| Stage | Typical duration | What drives it |
|---|---|---|
| Screening | 2 to 6 weeks | Availability of network data and the NSP's fault level information |
| Model assembly and benchmarking | 1 to 3 months | OEM model quality, NSP wide-area case, release of neighbour models |
| Full EMT study runs and reporting | 1 to 2 months | Number of scenarios, number of nearby plants, whether issues are found |
| NSP and AEMO review | 1 to 3 months or more | Reviewer workload, rounds of questions, any required model changes |
These ranges are indicative and vary widely between NSPs and regions.
Results and Remedies
A full assessment ends in one of three places: the plant is stable and causes no adverse impact, the plant needs changes to its own design or settings, or the plant's impact has to be remedied.
Inverter tuning
The cheapest fix is usually in the controls. Adjusting PLL bandwidth, current controller gains and the power plant controller's response can let a plant operate stably at a lower SCR. This needs the OEM to support the changes and to supply a re-validated model, and the revised settings then flow into the generator performance standards. It works well for marginal cases. It will not rescue a plant connected far below the inverter's capability.
Synchronous condensers
A synchronous condenser adds real fault current and inertia. It is proven and well understood, but adds capex, losses, maintenance and lead time, so it tends to suit large plants or hubs.
Grid-forming BESS
A grid-forming battery sets its own voltage reference rather than following the grid, and it can stabilise a weak connection in ways a grid-following inverter cannot. Where a project already includes a battery, specifying it as grid-forming is often the most economic option. AEMO's 2026 General Power System Risk Review, released in July 2026, found that grid-forming batteries are not yet confirmed as able to supply the fault current needed for minimum system strength, and AEMO is setting up a trial to build that evidence. Our comparison of grid-forming and grid-following inverters covers the technology in more depth. Expect to demonstrate the battery's contribution in the EMT studies, and do not assume it will be credited like a synchronous machine. Our guide to steady-state vs dynamic studies explains where these EMT cases sit in the wider study program.
Paying the system strength charge
Under the AEMC's system strength framework, transmission network service providers plan system strength centrally, and have been responsible for meeting the new standard since 2 December 2025. A connecting inverter-based plant can generally pay the TNSP's system strength charge instead of self-remediating, a choice that has applied since 2023. Our explainer on the system strength charge sets out how to weigh the two paths. The assessment does not disappear, though. The plant's capability, particularly the minimum SCR it can operate at, affects how much it draws on the service, and the plant must still be shown to operate stably.
Weak-Grid Areas and Site Selection
The cheapest system strength problem is the one avoided at site selection. Weak-grid areas share a pattern: long transmission lines, few nearby synchronous generators, and a cluster of inverter-based plant that used up the available fault level first. They often have the best resource and cheapest land, which is why they fill up.
Before committing to a site, it is worth getting:
- An indicative fault level and SCR at the candidate connection points, under minimum conditions.
- A list of committed and proposed inverter-based plant electrically nearby.
- An understanding of the TNSP's planned system strength solution for the region and when it is due.
- An early view of whether a co-located grid-forming battery would be part of the design anyway.
Early screening can change the connection point or inverter before either is locked in. Our solar farm site selection guide covers how grid factors sit alongside land, resource and planning constraints.
Commission a System Strength Impact Assessment
ElectraGlobe's power systems team carries out SCR screening, PSCAD model assembly and full system strength impact assessments for solar, wind and BESS connections across the NEM, and tests remedies such as inverter tuning and grid-forming batteries before they are committed to the design. See our steady-state and dynamic studies service, or contact us to discuss your connection.
Frequently Asked Questions
What is a short-circuit ratio?
The short-circuit ratio is the fault level at the connection point, in MVA, divided by the rated capacity of the connecting plant, in MW. It is a simple indicator of how strong the network is relative to the plant. As a rule of thumb, values below about 3 indicate a weak connection where grid-following inverters need careful study, but the inverter's own stated minimum SCR is the figure that matters.
When is a full system strength impact assessment required?
A full assessment is generally needed when screening shows thin margins between the connection point's SCR and the inverter's minimum, or when the plant shares a weak area with other inverter-based generators. The exact triggers are set by AEMO's guidance and the connecting NSP, and they have been revised under the current framework. Confirm them with the NSP at the start of the connection process.
How long does an SSIA take?
Screening can take a few weeks. A full EMT assessment, including model assembly, study runs, reporting and NSP review, commonly takes several months and can stretch further in congested weak-grid areas. Model quality and the release of neighbouring plant models usually drive the schedule more than the simulations themselves.
Can inverter tuning fix a system strength problem?
Often, if the problem is marginal. Retuning the PLL, current controllers and plant controller can let a plant run stably at a lower SCR, but the OEM must support the changes and supply a re-validated model. Tuning cannot overcome a connection far below the inverter's capability, where a synchronous condenser, a grid-forming battery or the system strength charge are the realistic options.