S5.2.5.15 Short Circuit Ratio Withstand: Proving Your Plant Works on a Weak Grid

S5.2.5.15 is the clause of Schedule 5.2 that requires an inverter-based plant to operate stably and remain connected down to a defined short circuit ratio (SCR): the three-phase fault level at the connection point divided by the plant's active power capability. The minimum access standard is an SCR of 3.0, assessed by the method in AEMO's System Strength Impact Assessment Guidelines (SSIAG). The performance standard records the lower of 3.0 and the value the plant can actually withstand.

There is no automatic access standard in the usual sense. The lower the SCR a plant can robustly demonstrate, the better its standard, and for projects that pay the system strength charge, the lower the charge.

What the Clause Requires

The clause applies only to asynchronous production units. The performance standard must record:

  • the agreed withstand SCR, which is the minimum of 3.0 and the value at which the plant has demonstrated stable operation
  • the active power capability or maximum demand, whichever is greater, used as the base for that ratio
  • any arrangements agreed if the plant cannot meet 3.0 on its own

Two provisions matter in practice. First, the capability may be demonstrated with different control or protection settings from those used for the other clauses. Second, a plant that cannot meet 3.0 can still comply if AEMO, the NSP and the System Strength Service Provider agree it has binding commitments to remedy the shortfall, by investing in its own plant or by procuring a service, plus operational arrangements for the meantime.

Why SCR Matters

Grid-following inverters synchronise to the network voltage with a phase-locked loop and inject current against it. When the grid is strong, the voltage barely moves as the inverter's current changes. When the grid is weak, every change in inverter current moves the voltage the inverter is trying to follow. Control loops that are stable at an SCR of 10 can oscillate or lose synchronism at 2.

The effect shows up in three ways:

  • Small-signal instability. Sustained oscillations after a minor disturbance, often in the range of a few hertz to tens of hertz.
  • Poor fault recovery. The plant rides through a fault but cannot re-establish stable current injection afterwards.
  • Voltage stability limits. At very low SCR, the network physically cannot transfer the plant's full power without unacceptable voltage, whatever the controls do.

Grid-forming inverters behave differently, holding their own voltage reference, and often demonstrate much lower withstand SCRs. They are not immune to the transfer limit.

The SSIAG Test Set

The SSIAG prescribes the demonstration. It is run in PSCAD on a single-machine infinite-bus system with the grid impedance set to give the target SCR at the site X/R. The test set typically includes:

TestWhat it shows
Long undisturbed flat run at the withstand SCRThe plant initialises and holds its operating point without drift or oscillation
Faults at the withstand SCR, across a range of retained voltagesThe plant rides through and recovers at that grid strength
Faults where the SCR drops from a strong value to the withstand value on clearanceThe plant survives losing a network element during the fault
Small voltage steps and short voltage impulsesSmall-signal stability and damping
Step change in grid impedance to the withstand valueThe plant tolerates a sudden weakening without a fault

Each test is repeated for every relevant operating mode: full export, full import for a battery, zero active power (STATCOM mode at night), and any hybrid modes. Fault performance at the withstand SCR must not fall below the minimum access standard for fault response.

Always check the current version of the SSIAG before running the tests. AEMO has refined the method, particularly for batteries in charging mode, and the version in force governs.

Batteries Charging at Very Low SCR

A battery absorbing its full rated power from a very weak grid hits a limit that is not a control problem at all. The network impedance limits how much power can flow to the connection point at an acceptable voltage. Applying an artificially high source voltage to make the case solve is not an acceptable workaround, and reviewers will reject it.

The accepted approach, in outline, is to set the source voltage within a realistic range so steady-state reactive power stays within the S5.2.5.1 capability, cap charging power at the maximum transferable for that SCR and X/R, and run a reduced set of tests in that state. The plant's withstand SCR is then recorded with the charging limitation that applies. Check the SSIAG version in force for the exact method.

The Commercial Lever

Under the system strength framework that started in 2022, a connecting plant chooses, in its connection application, between paying the system strength charge and remediating its own impact. That election is made once and cannot be changed later.

For projects that pay the charge, the quantity charged scales with the plant's withstand SCR multiplied by its rated power. Demonstrating a withstand SCR below 3.0 reduces that quantity roughly in proportion. The difference over a project's life can be substantial, which turns a technical study into a commercial decision.

That creates a temptation to push the number as low as possible. Two cautions:

  • The number must be robust. If the plant needs special settings to survive at the claimed SCR, those settings must be declared and carried into the GPS. If it only just survives in one test, expect challenge.
  • It interacts with other clauses. Settings that stabilise the plant at very low SCR can slow its voltage control or fault response at normal grid strengths. Check the consequences across S5.2.5.5A and S5.2.5.13 before committing.

Our article on the system strength charge explains the charge itself, and the system strength impact assessment covers the wider network study.

Choosing Grid Strength Cases for the Other Clauses

S5.2.5.15 is not the only place SCR matters. Almost every dynamic study is run at a maximum and a minimum grid strength. Common review points:

  • Use the agreed minimum SCR. Agree it with the NSP before studies start. Running the main studies at an inflated minimum to avoid instabilities is rejected, and so is reducing a neighbour's influence on paper.
  • Calculate from fault MVA directly. Use the NSP's minimum fault level under the agreed outage condition divided by rated power, with the site X/R.
  • Explain any intertrip. If the worst credible outage leaves an SCR the plant cannot handle, the NSP may accept an intertrip, more readily for a battery in charging mode than in discharge, but it will want evidence for each mode.

Get Your Withstand SCR Right

ElectraGlobe runs SSIAG withstand SCR demonstrations in PSCAD, works with OEMs on low-SCR tuning, and helps developers weigh the withstand value against fault response and voltage control. See our steady-state and dynamic studies service, or contact us.

Frequently Asked Questions

What is the minimum SCR in S5.2.5.15?

The minimum access standard requires inverter-based plant to operate stably and remain connected at a short circuit ratio of 3.0, assessed by the SSIAG method. The performance standard records 3.0 or the lower value the plant can demonstrate.

How is withstand SCR demonstrated?

By PSCAD simulation on a single-machine infinite-bus system, following the tests in AEMO's System Strength Impact Assessment Guidelines: a long flat run, faults at the withstand SCR, faults with a drop in SCR on clearance, voltage steps and impulses, and an impedance step, repeated for each operating mode.

Why does withstand SCR affect the system strength charge?

For a plant that elects to pay the system strength charge, the charged quantity is based on its withstand SCR multiplied by its rated power. A lower demonstrated withstand SCR therefore reduces the charge roughly in proportion.

Can a plant use special settings to meet S5.2.5.15?

Yes. The clause allows the capability to be demonstrated with control or protection settings that differ from those used for other clauses, but they must be declared and recorded, and their effect on the plant's other performance standards must be understood.