PSS/E and PSCAD Model Benchmarking: Why the Overlays Fail and How to Fix Them

PSS/E and PSCAD model benchmarking is the comparison of a plant's RMS model (PSS/E) and its EMT model (PSCAD) under the same set of disturbances, to show that the two describe the same plant. Results are overlaid case by case, differences are measured against tolerance bands, and every material difference is either fixed or explained. AEMO and NSPs rely on both models for different studies, so a plant whose models disagree leaves them unsure which one to trust.

Benchmarking is closely tied to AEMO's Dynamic Model Acceptance Test, and many of the same cases are used. It is where a lot of submissions lose review rounds.

Why Two Models Must Agree

PSS/E is used for wide-area studies across the NEM: large networks, many contingencies, long simulations. PSCAD is used where detail matters: fast control behaviour, unbalanced faults, weak grids and harmonics. Our article on EMT vs RMS simulation explains the difference.

The two tools approximate the plant differently, so some differences are expected, especially in the first cycles after a disturbance. What reviewers need is confidence that differences are understood and small enough not to change any conclusion drawn from either model.

How Benchmarking Is Done

Benchmarking Method

  • Use a single-machine infinite-bus test system built identically in both tools
  • Lock both models to the same firmware and parameter set, and record the versions
  • Run the same cases: balanced and unbalanced faults, voltage and frequency disturbances, setpoint steps, active power steps, phase angle steps
  • Run at minimum SCR, where differences are usually largest, and at maximum SCR
  • Overlay connection point voltage, active power, reactive power, reactive current and key internal signals
  • Derive tolerance bands, often from the EMT trace, and assess the RMS trace against them in defined windows
  • Tabulate the assessment for every case and explain every exceedance

Tolerance assessment is usually split into windows: before the disturbance, during it, the transition after it, and the settled post-disturbance period. Different tolerances apply to each, because the RMS model cannot reproduce the first few cycles of an EMT response.

Where Mismatches Cluster

Fault ride-through entry

In many inverter EMT models, entry into fault ride-through (or virtual impedance mode, in grid-forming plant) is triggered by a current threshold or an instantaneous quantity. The RMS model often uses a fixed voltage threshold instead. The two agree for deep faults, where every trigger fires, and disagree near the threshold, where the EMT model may enter the mode at a slightly different voltage depending on SCR and X/R. Discrepancies tend to cluster at faults that leave the terminal voltage near the threshold. The fix is either a better-aligned RMS trigger or a clear explanation with the mode flags plotted.

Temporary overvoltage

A switched capacitor in EMT produces an overvoltage spike and ringing that the RMS model cannot represent. RMS results typically show a smoother rise. Explain it, and make sure both models sustain the overvoltage for the required duration.

Low SCR

At minimum SCR, small differences in controller representation are amplified. Reactive and voltage steps can settle at slightly different levels, and transient responses can differ in damping. RMS models often appear better damped because they use lag approximations of transport delays that the EMT model represents exactly.

Other recurring areas

  • reactive power during frequency ramps
  • under-frequency transients
  • recovery from extended voltage dips
  • active power overshoot after fault clearance in grid-forming plant
  • unbalanced faults, where the RMS model has no negative sequence injection

What Reviewers Reject

The most common rejected argument is "both models settle at the same post-disturbance level, therefore the case passes". Reviewers want to know why the transient differs, what was done to improve alignment, and why further improvement is not possible. Other recurring comments:

Reviewer concernWhat they want to see
Unexplained mismatchRoot cause for each exceedance, not a general statement
Citing OEM adviceThe OEM letter or email itself, supplied with the report
Mode differences hiddenFault ride-through and mode flags plotted alongside the main quantities
Axis scalingAxes that show every spike, not clipped to make overlays look closer
Inconsistent labelsTables, case names and SCR labels that match the files submitted
Version driftEvidence that both models use the same firmware and parameters
Internal signalsConfirmation from the OEM that monitored internal signals are the correct ones

Version Locking Prevents Most Problems

The commonest root cause of a mismatch is not physics. It is two models built from different versions. The OEM updates the PSCAD model for a firmware change and the PSS/E model lags behind, or the plant controller model is built separately for each tool by different people from different documents.

Keep a single parameter register mapping every setting to its name in the PSS/E model, the PSCAD model and the data sheets. When anything changes, update both models and re-run the benchmark. Our article on the PSCAD model package and releasable user guide covers the documentation side.

Writing the Benchmarking Report

A benchmarking report that passes first time is organised around the reviewer's questions, not the order the simulations were run. A structure that works:

  1. A summary table listing every case, the windows assessed, and pass or exceedance for each quantity.
  2. A section for each group of cases, with overlays at the same scale for both tools and the tolerance band drawn on the chart.
  3. For each exceedance, a short explanation: the mechanism, the evidence (internal signals, mode flags, OEM confirmation), the steps taken to reduce it, and why the residual difference does not change any study conclusion.
  4. An appendix recording model versions, firmware, time steps, solver settings and the test system parameters.

Keep case names identical to the file names in the submitted package. A reviewer who cannot match a plot to a simulation file will ask, and every question costs a round.

Benchmarking Against Site Data

Model-to-model benchmarking is followed later by model-to-plant validation. After energisation, the hold point tests produce measured responses to setpoint steps and disturbances, and the models are overlaid on them for R2 validation. A pair of models that agreed with each other but not with the plant will have to be revised then, which is why getting settings right at the start matters. Our overview of PSS/E and PSCAD modelling for renewables explains where each step sits.

Get Benchmarking Done Right

ElectraGlobe builds and benchmarks PSS/E and PSCAD models for solar, wind and BESS connections, resolves mismatches with OEMs, and prepares benchmarking reports that answer reviewers' questions in advance. See our steady-state and dynamic studies service, or contact us.

Frequently Asked Questions

What is model benchmarking?

It is the comparison of a plant's PSS/E (RMS) and PSCAD (EMT) models under identical disturbances, with results overlaid and differences assessed against tolerance bands, to show the two models represent the same plant.

Why don't PSS/E and PSCAD results match exactly?

They use different modelling approaches. PSCAD solves instantaneous waveforms with small time steps and represents fast control and unbalance in detail; PSS/E solves positive sequence phasors with larger steps. Some differences, especially in the first cycles after a disturbance, are expected and must be explained.

What is the most common benchmarking failure?

Models built from different firmware or parameter versions. After that, fault ride-through entry logic that uses a current trigger in the EMT model and a voltage threshold in the RMS model, giving different behaviour near the threshold.

Is matching post-disturbance levels enough to pass?

Usually not. Reviewers expect the transient differences to be explained, with the steps taken to improve alignment and the reason further improvement is not possible.

Power System Studies

Steady-state and dynamic studies in PSS/E and PSCAD, giving AEMO and your network service provider the technical evidence they need to approve connection, GPS applications and registration.

Learn more