The PSCAD Model Package and Releasable User Guide: What NSPs and AEMO Expect

A releasable user guide (RUG) is the document that accompanies a plant's simulation model and lets someone outside the project, such as AEMO, the NSP or another connecting party, set up and run the model correctly. Together with the PSCAD model files, the PSS/E model, a parameter sheet and supporting data, it forms the model package that every NEM connection must submit. The model package is reviewed as carefully as the studies, because NSPs and AEMO will use it for years in their own analysis of the network.

Most model package review comments are not about engineering. They are about missing information and inconsistency between documents.

What the Model Package Contains

ItemPurposeCommon gaps
PSCAD model filesEMT representation of the plant for detailed studiesLibrary or compiler version mismatch; missing revision in the file name
PSS/E model filesRMS representation for wide-area studiesOut of step with the PSCAD firmware version
Releasable user guideInstructions to set up, initialise and run the modelRefers to non-public OEM documents; missing set-up steps
Parameter sheetEvery control, limit and ramp setting with its valueMissing entries; units or base not stated
Functional block diagramsHow the inverter and plant controller controls are structuredNot supplied, or supplied late
Data sheetsTransformer, cable, inverter and auxiliary dataDifferent values from the model
Model acceptance test resultsEvidence the model behaves crediblyRun on a different model version

What a Releasable User Guide Should Cover

The word releasable matters. The RUG must be able to stand alone and be shared with parties who have no access to the OEM's confidential documentation. A RUG that says "see the OEM manual" for a key set-up step is not releasable.

Releasable User Guide Contents

  • Site information and a connection single line diagram
  • Key plant data: inverter type and number, plant controller, transformers, collector network
  • Description of each control function: voltage and reactive control, active power and frequency control, fault ride-through, protection
  • How droop and ramp settings are implemented, including the base used and how it scales with units in service
  • List of model libraries, with versions and the compiler and PSCAD versions they were built with
  • Recommended simulation time step and any constraints from the OEM
  • Step-by-step set-up and initialisation instructions, including how to set an operating point
  • Parameter tables for the inverter and plant controller, or a reference to the separate parameter sheet
  • Known limitations of the model
  • A statement on any black-box or encrypted components and what they contain

Technical Requirements That Catch People Out

Compiler and version compatibility

PSCAD models built with compiled libraries depend on the PSCAD version and the Fortran compiler used to build them. A library compiled for one environment may not run in another. State the versions clearly and, where possible, provide libraries for the versions the NSP and AEMO use. Build errors from a 32-bit and 64-bit compiler mismatch are a familiar review comment.

Time step

OEM models are often validated at a specific time step. Some will run only at specific values. State the permitted values in the RUG, and make sure the studies used one of them.

Initialisation

Reviewers expect a model to initialise quickly and cleanly to any operating point specified. AEMO's expectations for initialisation time are short, measured in a few seconds of simulated time. A model that takes much longer will be queried, and the applicant asked to explain why it cannot be improved. Models that cannot initialise directly at very low SCR, and need to start strong and ramp down, should say so in the RUG.

Snapshots and repeatability

PSCAD models should support snapshots, so long studies can start from an initialised state. Consecutive flat runs should be identical.

Simulation speed

Detailed EMT models can be slow. AEMO has expectations on the speed of models relative to real time for use in large studies. Very slow models are a problem for wide-area EMT analysis and may be queried.

Consistency Is Checked Line by Line

Reviewers cross-check every number that appears in more than one place. Typical sources of inconsistency:

  • transformer ratings or impedances that differ between the data sheet, the RUG and the model
  • a controller gain in the RUG that differs from the configuration file
  • impedances in ohms in one document and per unit in another
  • ramp rates in percent per second of plant MVA in the model and megawatts per minute in the access standard
  • active and reactive power limits in the parameter sheet that do not match the GPS or access standard
  • protection settings in the model that differ from the protection settings report

The fix is a single master parameter register, maintained by one person, from which every document is generated or checked before each submission. Include the revision number in every model file name and every document, so there is never doubt about which version a result came from.

Functional Block Diagrams

Reviewers frequently ask how the plant actually responds: what triggers fault ride-through, whether the plant changes mode or freezes its control loops, how the plant controller and inverters hand over control during a disturbance, and how negative sequence and current limits are handled. The answers live in the functional block diagrams of the inverter and plant controller. Supplying them with the first submission, rather than in response to a query, saves a review round. Where source code exists, OEMs commonly offer it directly to AEMO on request.

Distribution Connections

DNSPs reviewing embedded generators ask for much the same package at smaller scale: the PSCAD model, a user guide, a parameter sheet with every power, ramp and limit setting, and a model acceptance checklist. Missing maximum and minimum power and ramp rate entries in the parameter sheet are a common comment. The DNSP will expect the final OEM parameter list before commissioning. See our guide to Chapter 5A connection access standards.

Model Packages Live Beyond the Connection

The model package is used long after the connection is agreed. It is updated at R1 against final design, validated at R2 against site tests, and used by AEMO and NSPs in their planning and operational studies for the life of the plant. Firmware changes after commissioning can require an updated model. A model package that is well structured from the start is far cheaper to maintain. Our article on PSS/E and PSCAD model benchmarking covers the comparison between the two models, and PSS/E and PSCAD modelling for renewables the wider picture.

Get a Model Package That Passes Review

ElectraGlobe prepares PSCAD and PSS/E model packages, releasable user guides and parameter registers for solar, wind and BESS connections, and works with OEMs to close model queries. See our steady-state and dynamic studies service, or contact us.

Frequently Asked Questions

What is a releasable user guide?

It is the document that accompanies a plant's simulation model and explains how to set it up, initialise it and run it. It must be releasable, meaning it can be shared with third parties such as AEMO and NSPs without relying on confidential OEM documentation.

What goes in a PSCAD model package?

The PSCAD model files and libraries, the PSS/E model, a releasable user guide, a parameter sheet listing every control and limit setting, functional block diagrams, data sheets and model acceptance test results.

Why do model packages get rejected?

Most often for inconsistency between documents, such as different transformer data or controller settings in the RUG, the model and the data sheets, and for missing information such as compiler versions, set-up steps or block diagrams.

How long should a PSCAD model take to initialise?

AEMO expects models to initialise within a few seconds of simulated time. A model that takes significantly longer will usually be queried, and the applicant asked to explain why it cannot be improved.